Generators & Temporary Power

Generator installation, earthing, fuel storage, ventilation, noise, transfer switching, and DEWA/ADDC connection requirements for UAE construction sites.

Generator Regulatory Requirements

Generators used as temporary power sources on UAE construction sites are subject to requirements from multiple authorities. The Abu Dhabi DoE EWR 2020 covers the electrical installation aspects. The UAE Fire and Life Safety Code of Practice (Civil Defense) covers fuel storage and fire safety. ADOSH-SF CoP 15.0 covers occupational safety. Local municipality building permits are required for permanent or semi-permanent generator installations.

  • Electrical installation

    DoE EWR 2020 (Abu Dhabi) / Dubai Building Code 2021

    critical
  • Fire safety / fuel storage

    UAE Fire and Life Safety Code of Practice

    critical
  • OSH requirements

    ADOSH-SF CoP 15.0

    critical
  • Noise limits

    Local municipality requirements — typically 55 dB(A) daytime

    standard
  • Permit

    Municipality building permit required for semi-permanent installation

    critical

Generator Siting and Installation

Generators must be sited to minimise fire risk, noise impact, and exhaust fume exposure to workers. On UAE construction sites, generators must be positioned at least 3 m from any building, combustible material, or fuel storage. Exhaust outlets must be directed away from occupied areas and air intakes. Anti-vibration mounts must be used to prevent structural damage.

  • Minimum distance from buildings

    3 m (5 m from fuel storage)

    critical
  • Exhaust direction

    Away from occupied areas, air intakes, and openings

    critical
  • Ventilation

    Adequate air supply for combustion and cooling — no enclosed spaces

    critical
  • Anti-vibration mounts

    Required to prevent structural transmission

    standard
  • Bunded fuel tank

    110% containment bund required for diesel storage

    critical
  • Fire extinguisher

    CO₂ or dry powder extinguisher within 5 m of generator

    critical

Transfer Switching

Where a generator is used as a standby or alternative supply alongside a utility (DEWA/ADDC) supply, a proper automatic or manual transfer switch (ATS/MTS) must be installed to prevent back-feeding the utility network. Back-feeding is a serious safety hazard for utility workers and is illegal under DEWA and ADDC regulations. The transfer switch must provide a mechanical and/or electrical interlock preventing simultaneous connection of both supplies.

  • Transfer switch type

    ATS or MTS with mechanical interlock — no parallel operation

    critical
  • Back-feed prevention

    Mandatory — illegal to back-feed DEWA/ADDC network

    critical
  • Neutral switching

    4-pole transfer switch required (switches neutral)

    critical
  • DEWA/ADDC notification

    Generator installation must be notified to supply authority

    critical

Back-feeding the utility network can kill utility workers working on what they believe to be a dead line. This is a criminal offence under UAE law. Always use a properly interlocked transfer switch.

Fuel Storage

Diesel fuel storage for generators on UAE construction sites is regulated by the UAE Fire and Life Safety Code of Practice. Fuel must be stored in approved containers or tanks with secondary containment bunding. Quantities above 450 litres require a Civil Defense permit in most emirates.

  • Approved fuel containers

    UN-approved containers only — no improvised storage

    critical
  • Bunding

    110% of tank capacity — impermeable bund

    critical
  • Civil Defense permit

    Required for >450 litres storage (most emirates)

    critical
  • No smoking

    No smoking within 10 m of fuel storage

    critical
  • Earthing of fuel tanks

    Static earthing required for metal fuel tanks

    critical