Training library
New in 2026

Module sections: ground works, high-risk controls, access at height and site handover

These 35 modules are a sequence, not an alphabet. Work through a section in order and your team covers one complete part of the job — from temporary works design to the final authority notification.

Sections
8
Modules
35
Total runtime
9.7 h
Series research notes & sources (Markdown)

Section 1

Excavation & Temporary Works

Designing, installing and releasing the support system — deep excavation design intent, sheet piling, shoring, propping and staged strut removal.

5 modules 108 min Temporary works coordinator, site engineer, excavation supervisor
  1. 1.1Deep Excavation & Temporary Works

    12 min

    The parent work package for deep excavation: geotechnical and groundwater investigation, temporary-works design and independent check, excavation sequencing, stability, access and emergency controls.

    Start module
  2. 1.2Sheet Piling, Shoring & Propping

    12 min

    Installation and extraction of sheet piles, pile-driving hazards, lifting and rigging, walings, struts, tie rods and anchors, monitoring and alteration control.

    Start module
  3. 1.3Intermediate Shoring Stage Release & Authority Submission (Dubai / Abu Dhabi DMT)

    26 min

    Decide correctly what must be produced, signed and submitted before releasing an intermediate shoring level — Dubai Municipality and DDA third-party review rules, Abu Dhabi DMT permit classification, the 11-record stage release pack and the authority submission decision logic.

    Start module
  4. 1.4Shoring & Strut Removal: Strength Verification, Consultant Sign-off and SIMOPS

    30 min

    There is no universal UAE percentage that authorises strut or temporary-shoring removal. Covers the seven release gates, the auditable strength-verification and consultant sign-off pack, Dubai's written-consent rule for anchor removal, and the SIMOPS control matrix for earthmoving, crane lifting, formwork and dewatering inside a retained excavation.

    Start module
  5. 1.5Work Inside an Active Excavation (Foundations, Walls, Scaffold, Pours)

    28 min

    Excavation controls do not end when foundations, basement walls, formwork or scaffolding begin — they layer. Covers retained excavation controls, activity-specific release controls, SIMOPS coordination, the cumulative permit/release stack and the formal tests for reducing or withdrawing excavation controls.

    Start module

Section 2

Dewatering & Discharge Compliance

Groundwater control from pump selection through to the emirate-specific discharge approval and the environmental conditions attached to it.

4 modules 55 min Dewatering contractor, environmental officer, HSE manager
  1. 2.1Construction Dewatering & Groundwater Control

    11 min

    Dewatering design, wellpoints, deep wells and sump pumping, standby pumps, temporary electrical supply, drawdown and settlement control, monitoring, shutdown and system removal.

    Start module
  2. 2.2Dewatering Discharge & Environmental Compliance

    10 min

    Authority approvals and NOCs for discharge, water-quality sampling and testing, silt and oil removal, discharge-point control, tanker off-haul, spill response and record keeping.

    Start module
  3. 2.3Municipal Dewatering & Groundwater-Discharge Approvals (UAE)

    10 min

    Jurisdiction-by-jurisdiction approval routes for construction dewatering and groundwater discharge in Abu Dhabi, Dubai (DDA and municipal/waterway areas) and Sharjah, plus the permit register and site compliance controls.

    Start module
  4. 2.4Electrical Dewatering-Pump PTW & LOTO Isolation

    24 min

    Isolate an electrical dewatering pump safely under a controlling permit — energy source identification, standby resilience, lock-out execution, voltage proving, try-start verification and controlled return to service.

    Start module

Section 3

Monitoring & Adjacent Structures

Instrumentation, Alert / Action / Alarm trigger levels, underground services and the audit trail that proves the readings were acted on.

3 modules 44 min Instrumentation engineer, consultant, HSE auditor
  1. 3.1Underground Services, Adjacent Structures & Monitoring

    10 min

    NOCs and utility protection, pre-condition surveys, inclinometers and settlement markers, vibration and noise monitoring, exclusion zones, public protection and traffic management.

    Start module
  2. 3.2Excavation Monitoring Trigger Levels (Alert–Action–Alarm)

    22 min

    Build a defensible Alert–Action–Alarm trigger register for inclinometers and piezometers on deep excavations — formula rules, stage-specific alarm values, reading validity and the PTW response at each level.

    Start module
  3. 3.3Excavation Monitoring Framework & Contractor Audit

    12 min

    Soil and groundwater monitoring requirements for the excavation safety plan — instruments, baselines, trigger-action-response — and a contractor audit checklist with critical audit-fail conditions.

    Start module

Section 4

Permits, SIMOPS & Verification

Where the permit-to-work system meets simultaneous operations — crane lifts above formwork, exclusion zones and concrete strength verification before release.

3 modules 73 min Permit issuer, lifting supervisor, QA/QC engineer
  1. 4.1Deep Excavation & Sheet Piling: High-Risk Interfaces and PTW

    13 min

    How the primary excavation permit-to-work links to utility NOCs, isolation certificates, confined-space entry, hot work, critical lifts, dewatering discharge approvals and road/traffic permits under ADOSH-SF CoP 21.0 and CoP 29.0.

    Start module
  2. 4.2In-Situ Concrete Verification & Crane-Above-Formwork SIMOPS

    30 min

    How to qualify a third-party testing laboratory to ISO/IEC 17025:2017 for the exact test method, where rebound hammer and UPV legitimately sit in a shoring-release decision, when cores are required, and how to run crane lifting above active internal formwork floors without putting anyone under a suspended load.

    Start module
  3. 4.3SIMOPS Incident Reporting & Crane–Formwork Exclusion-Zone Audit

    30 min

    Working compliance procedure for notifying and investigating a major SIMOPS incident in the UAE — emergency services, MOHRE, Abu Dhabi Form G / Form G1 and municipal permit routes — together with the crane-above-formwork exclusion-zone audit that keeps crews out of the lift and fall envelope. Working compliance analysis, not legal advice: verify live permit conditions and authority routing with a qualified UAE legal/HSE professional.

    Start module

Section 5

Emergency, Rescue & Casualty Response

The scenarios that decide whether an excavation incident becomes a fatality — flooding and collapse, lower-basement evacuation, multi-casualty triage and CoP 46.0 extraction equipment.

5 modules 114 min Emergency response team, first aiders, rescue team leader
  1. 5.1Flooded Excavation Collapse: Emergency Response & Rescue

    12 min

    Activation thresholds, command structure, timed immediate actions, rescue prerequisites and no-go conditions, stabilisation tactics, notifications and PTW restoration for a flooded or collapsed deep excavation.

    Start module
  2. 5.2Lower-Basement Emergency Evacuation & Rescue During Lifting and Concreting

    30 min

    Emergency evacuation and rescue for congested internal lower-basement workfaces where heavy lifting, concrete pumping, formwork and reinforcement, dewatering and retained-excavation controls run at the same time — pre-start rescue release gate, SIMOPS emergency zoning, the all-stop sequence, controlled casualty transfer and the drill that proves it.

    Start module
  3. 5.3Multi-Casualty Lower-Basement Medical Response, Evacuation & SIMOPS Enforcement

    32 min

    Project-adaptation procedure for a congested lower-basement workface where a collapse, crane incident, falling object, formwork failure, fire or flood produces multiple actual or potential casualties: readiness gate, alarm and zoning clock, triage and casualty movement, command roles, and an NC-1 to NC-5 enforcement matrix that separates authority sanction from contractual remedy. Not a substitute for emergency-service instruction, the approved emergency plan, fire/life-safety design or contract review.

    Start module
  4. 5.4CoP 46.0 Worker Extraction & Rescue Equipment for Confined Lower-Basement Conditions

    28 min

    What ADPHC CoP 46.0 actually mandates for first aid, casualty movement, evacuation, rescue capability and extraction equipment underground — plus the scope-applicability question for a conventional lower basement, the 25-person rescue-team trigger, workforce scaling, and the NC severity / enforcement split. Reports the Code's stated provisions; it does not add generic standards the Code does not state, and it is not a substitute for the approved emergency plan or authority confirmation.

    Start module
  5. 5.5Continuous Deep Excavation & Dewatering: Handover and Rescue Readiness

    12 min

    Shift-change and contractor handover for continuous deep excavation and dewatering, plus the emergency-response and rescue prerequisites that must be verified before the controlling PTW is issued.

    Start module

Section 6

Mobilisation, Demobilisation & Authority Handover

The two ends of the project — setting the site up against authority requirements, then closing utilities, environmental obligations and notifications on the way out.

3 modules 80 min Project manager, HSE manager, commercial / handover lead
  1. 6.1Site Mobilisation, Demobilisation & Client Handover — UAE Authority Readiness

    30 min

    Jurisdiction-first readiness control for UAE projects: resolve the controlling authority before issuing any checklist, then run the M-01 to M-20 mobilisation gate, the D-01 to D-24 demobilisation, closeout and client-handover register, the timeframe model and the management dashboard. A planning and evidence-management tool — verify requirements, portals, fees and inspection availability with the appointed consultant and responsible authority before formal submission.

    Start module
  2. 6.2Final Utility & Environmental Clearance — Demobilisation and Client Handover

    26 min

    The Final Utility & Environmental Clearance gate that sits before temporary services, welfare, equipment or environmental controls are removed: select the utility end state first, then run the conditional Dubai, Abu Dhabi and Sharjah authority controls, the UE-01 to UE-20 clearance checklist and the planning-versus-authority-timing model. A configurable project-control checklist and management teaching aid — not legal advice, and not a substitute for current authority, utility or permit-condition confirmation.

    Start module
  3. 6.3Authority Notification & Industrial / Free-Zone Utility Handover — Final Site Clearance

    24 min

    How to notify Dubai Municipality, Abu Dhabi Municipality / DMT, EAD or a free-zone authority for final site clearance and environmental handover, and how to run the PM-01 to PM-20 permanent utility handover and meter-closure checklist across industrial and free-zone jurisdictions. Includes the editable email template, mandatory attachment schedule and the decision matrix that separates a permanent-meter transfer from a permanent-meter removal.

    Start module

Section 7

High-Risk Construction Controls

The critical-control activities that cause most UAE construction fatalities — life-saving rules, hot work, gas cylinders, lifting and rigging, mobile plant interfaces, silica dust, temporary power and demolition.

8 modules 72 min Site supervisor, permit issuer, HSE officer, lifting supervisor
  1. 7.1Critical Controls & Life-Saving Rules

    8 min

    Introduces the concept of critical risk and life-saving rules used across UAE construction majors, and how bow-tie critical controls prevent fatalities from working at height, lifting, confined space, energy isolation and vehicles.

    Start module
  2. 7.2Hot Work, Welding, Cutting & Fire Watch

    8 min

    Covers UAE hot work permit requirements, welding and cutting hazard controls, fire watch duties, and Civil Defence coordination for construction and fit-out sites.

    Start module
  3. 7.3Gas Cylinders, Oxy-Fuel Equipment & Compressed Gas Storage

    8 min

    Covers the safe handling, transport, storage and use of compressed gas cylinders and oxy-fuel welding/cutting equipment on UAE construction sites, including segregation, flashback arrestors and desert climate hazards.

    Start module
  4. 7.4Lifting Accessories, Slinging, Rigging & Banksman Signalling

    10 min

    Covers safe use of lifting accessories, sling angle and load calculations, rigging inspection, exclusion zones, and standard banksman/signaller hand signals required on UAE construction lifting operations.

    Start module
  5. 7.5Mobile Plant, Reversing Operations & Pedestrian Segregation

    10 min

    Controlling the interface between mobile plant and pedestrians on UAE construction sites — traffic management plans, banksman procedures, reversing controls and segregation infrastructure required under ADOSH-SF (formerly OSHAD) and Dubai Municipality codes.

    Start module
  6. 7.6Respiratory Protection & Silica Dust Control

    10 min

    Managing respirable crystalline silica (RCS) and other airborne hazards on UAE construction sites: exposure sources, the control hierarchy, respirator selection, fit testing and health surveillance under ADOSH-SF (formerly OSHAD) requirements.

    Start module
  7. 7.7Temporary Electrical Installations, Distribution Boards & Portable Tools

    10 min

    Safe design, inspection and use of temporary electrical supplies on UAE construction sites — distribution boards, RCD protection, cable management and portable appliance testing, aligned to DEWA/ADDC rules and ADOSH-SF (formerly OSHAD) requirements.

    Start module
  8. 7.8Demolition, Dismantling & Structural Alteration Safety

    8 min

    Planning and controlling demolition, dismantling and structural alteration works on UAE sites — surveys, method statements, structural stability, exclusion zones and utility isolation under Dubai Municipality and Trakhees CSR requirements.

    Start module

Section 8

Access, Height & Work Over Water

Getting people safely to the workface and back — facade and rope access, ladders and step platforms, MEWPs and boom lifts, plus marine interfaces and drowning prevention.

4 modules 34 min Working-at-height supervisor, access coordinator, marine works supervisor
  1. 8.1Facade Access, Rope Access & Suspended Platforms

    8 min

    Covers IRATA/SPRAT rope access discipline, suspended (cradle/BMU) platforms and facade maintenance access on UAE high-rise towers, aligned with ADOSH-SF (formerly OSHAD) and Dubai Municipality high-rise access requirements.

    Start module
  2. 8.2Safe Use of Ladders & Step Platforms

    8 min

    Practical guidance for selecting, inspecting and safely using ladders, step ladders and podium steps on UAE construction sites, in line with Dubai Municipality Code of Construction Safety Practice and ADOSH-SF (formerly OSHAD) hierarchy-of-controls expectations.

    Start module
  3. 8.3Mobile Elevated Work Platforms & Boom Lifts

    10 min

    MEWP and boom lift operation, pre-use checks, exclusion zones and rescue planning for UAE construction and infrastructure sites, referencing IPAF certification and ADOSH-SF (formerly OSHAD) / Dubai Municipality access equipment requirements.

    Start module
  4. 8.4Work Over Water, Marine Interfaces & Drowning Prevention

    8 min

    Controls for construction and marine works over or adjacent to water in the UAE — jetties, dredging, marine piling and coastal reclamation — covering lifejackets, rescue craft and Federal Transport Authority / port authority marine rules.

    Start module

Editable packs that go with these sections

Toolbox decks, trigger-level workbooks, SIMOPS control packs, rescue dashboards and the mobilisation / demobilisation workbook are all on the ground works briefing page.