Scaffolding
Design, erection, scafftag inspection regimes, tube-and-fitting and system scaffolds, mobile towers, loading limits and ties — to ADOSH-SF CoP 26.0, DM Code of Construction Safety Practice, BS EN 12811 and BS 5975.
Scaffold Design and Competence
Scaffolds must be erected, altered and dismantled only under the supervision of a competent scaffold supervisor by trained scaffolders. Any scaffold that is not a basic configuration to a recognised standard configuration guide must be designed and calculated by a competent engineer, with drawings on site. Dubai Municipality and Trakhees require third-party-certified scaffolders and inspectors for major projects.
Scaffolder competence
Recognised scaffolding certification (e.g. CISRS or equivalent third-party card)
criticalScaffold supervisor
Named, competent, present during erection, alteration and dismantling
criticalDesign required when
Height >8 m free-standing, non-standard configuration, loading >2 kN/m², cantilever, birdcage over voids, sheeted/netted scaffolds
criticalDesign documents on site
Stamped drawings and calculations available for inspection
criticalStandard configuration reference
BS EN 12811-1 / BS 5975 / TG20-style compliance sheet
standard
Dimensional and Component Requirements
| Element | Requirement | Reference |
|---|---|---|
| Main guardrail height | 950–1,150 mm above the platform | BS EN 12811-1 / ADOSH-SF CoP 26.0 |
| Maximum bay length | 2.4 m (tube-and-fitting) / 2.5 m (system scaffold) | ADOSH-SF CoP 26.0 |
| Maximum lift height | 2.0 m between platform levels | ADOSH-SF CoP 26.0 |
| Intermediate guardrail | Max unprotected gap 470 mm | BS EN 12811-1 |
| Toe board | Minimum 150 mm high, fitted to all open edges | BS EN 12811-1 / DM Code |
| Platform width — general access | Minimum 600 mm clear (3 boards) | ADOSH-SF CoP 26.0 / BS EN 12811-1 |
| Platform width — with materials | Minimum 900 mm clear (4–5 boards) | BS EN 12811-1 |
| Gap between platform and structure | Maximum 300 mm, otherwise infill or edge protection | ADOSH-SF CoP 26.0 |
| Board overhang at supports | Minimum 50 mm, maximum 4x board thickness | BS 5975 |
| Base plates / sole boards | Mandatory on all standards; sole boards on sand or soft ground | BS EN 12811-1 |
| Tie spacing | Per design; typically every 4 m vertically and horizontally on sheeted scaffolds | BS 5975 |
| Ladder access rise | Landing/rest platform at maximum 9 m vertical intervals | ADOSH-SF CoP 26.0 |
Sheeting or debris netting dramatically increases wind load. A scaffold designed unsheeted must never be sheeted without a re-design and additional ties — this is one of the most common collapse causes in the region.
Load Classes
Load class displayed
Stated on the scafftag and design sheet
criticalLoaded bays
Only bays designed for material storage may be loaded
criticalSimultaneous loaded lifts
Per design — commonly one loaded lift per bay
standard
| Class | Uniform load | Typical use |
|---|---|---|
| 1 | 0.75 kN/m² | Inspection and very light access only |
| 2 | 1.50 kN/m² | Light duty — painting, cleaning, rendering touch-up |
| 3 | 2.00 kN/m² | General duty — most construction trades |
| 4 | 3.00 kN/m² | Heavy duty — masonry, blockwork |
| 5 | 4.50 kN/m² | Very heavy — stone/heavy cladding storage |
| 6 | 6.00 kN/m² | Special design — engineer calculation mandatory |
Scafftag Inspection Regime
Every scaffold must carry a tag at each access point showing its status. A scaffold under erection, alteration or dismantle carries a red 'Do Not Use' tag with the tie/board status; only when a competent inspector has signed it off does it carry a green tag.
Inspection before first use
By a competent inspector, recorded and tagged
criticalRoutine inspection interval
Every 7 days maximum — ADOSH-SF CoP 26.0
criticalHandover certificate
Scaffold handover certificate issued and signed by the competent scaffold inspector before first use — ADOSH-SF CoP 26.0
criticalAdditional inspections
After alteration, impact, high wind, sandstorm or rain event
criticalRecord retention
Inspection register kept on site for the project duration
standardTag content
Scaffold ID, load class, inspector name, date, next inspection due
criticalIncomplete scaffold
Red tag and physical access blocked at every ladder/stair
critical
Mobile Access Towers
Mobile aluminium towers must be assembled strictly to the manufacturer's instruction manual using an advance-guardrail or through-the-trap method, so the erector is never exposed to an unguarded edge.
Assembly method
Advance guardrail (AGR) or 3T through-the-trap only
criticalHeight-to-base ratio — indoor
Maximum 3.5:1
criticalHeight-to-base ratio — outdoor
Maximum 3:1
criticalStabilisers / outriggers
Fitted per the manual before the tower is climbed
criticalCastors
Locked while in use; never move the tower with a person or materials on it
criticalAccess
Internal ladder only — never climb the outside frame
criticalManual on site
Manufacturer instruction manual available at the tower
standard