Trade Packs, Public Interface & CEMP Assurance

The three places where UAE projects most often meet somebody else's rules: the high-risk trades that need a designed sequence, the public who walk and drive past your hoarding, and the environmental commitments in your approved CEMP. Work each register item by item, note the evidence, export or print for the file.

Register items
44
In scope
44
Verified
0
Failures open
0

Project and phase

Structural steel erection, precast and tilt-up, concrete pumping and placement, forklift and telehandler.

Trade packs register

Stream
  • ST-01 · Structural steel erection · Per erection zone / per revision

    Erection method statement matches the designer's sequence

    Open

    The erection sequence, temporary stability scheme and crane positions in the method statement are the ones the structural designer signed off — any field deviation goes back through management of change before steel moves.

    Owner: Steel subcontractor engineer · Evidence: Stamped erection drawings + approved MS/RA revision

  • ST-02 · Structural steel erection · Every lift release

    Temporary bracing and guys installed before release

    Open

    No lifting accessory is released from a member until the specified temporary bracing, guys or bolted connections are installed and checked by the erection supervisor.

    Owner: Erection supervisor · Evidence: Release checklist signed per member/frame

  • ST-03 · Structural steel erection · Per connection lot

    Bolt torque and weld inspection records closed out

    Open

    Bolting torque records and weld NDT reports are collected per connection lot and reconciled against the erection drawings before the frame is loaded out or decked.

    Owner: QA/QC engineer · Evidence: Torque log, NDT reports, inspection & test plan sign-off

  • ST-04 · Structural steel erection · Daily before work

    Fall protection: anchorage designed, not improvised

    Open

    Static lines, anchor points and net systems used at height are specified with rated capacity, installed by trained persons and inspected before each shift — steel members are not used as anchors unless the designer allows it.

    Owner: HSE officer / erection supervisor · Evidence: Anchorage design note + pre-use inspection tags

  • ST-05 · Structural steel erection · Each shift and each move

    Exclusion zone under and around the erection front

    Open

    The drop zone is barricaded, signed and manned; no other trade works under or adjacent to live erection, and the boundary is re-set each time the erection front moves.

    Owner: Site supervisor · Evidence: Daily zone plan / permit with barricade photos

  • PC-01 · Precast & tilt-up · Per element type

    Lifting inserts and rigging verified against element data

    Open

    Each element's mass, centre of gravity, insert type and rated capacity are confirmed against the manufacturer's data sheet before rigging; only matched, certified lifting clutches are used.

    Owner: Lifting supervisor · Evidence: Element data sheet + rigging register

  • PC-02 · Precast & tilt-up · Per pour / per element

    Concrete strength confirmed before lift or prop release

    Open

    Lift-off and prop-removal only after test results confirm the strength stated in the design (field-cured cubes/cylinders, not the 28-day default) — recorded against the element reference.

    Owner: QA/QC engineer · Evidence: Cube/cylinder test certificates keyed to element IDs

  • PC-03 · Precast & tilt-up · Per element until permanent connection

    Propping design, install and removal controlled

    Open

    Temporary props follow a designed layout with specified capacity, base fixings and wind case; removal is authorised in writing by the temporary works coordinator only.

    Owner: Temporary works coordinator · Evidence: Prop layout drawing, install check, removal permit

  • PC-04 · Precast & tilt-up · Continuous during lifts

    Wind limits and stability during erection

    Open

    A wind speed limit for panel handling is set from the element area and rigging arrangement, measured on site, and erection stops when it is exceeded — not judged by feel.

    Owner: Lifting supervisor · Evidence: Anemometer log against stated limit

  • PC-05 · Precast & tilt-up · Weekly and on delivery

    Storage, stillages and transport on site

    Open

    Panels are stored in designed stillages or racks on prepared ground, with no leaning stacks, and internal transport routes are checked for grade, edge proximity and overhead services.

    Owner: Site logistics · Evidence: Storage area layout + weekly inspection

  • CP-01 · Concrete pumping & placement · Every set-up

    Outrigger ground bearing assessed and matted

    Open

    Boom pump set-up point has a ground bearing assessment covering backfill, basements, culverts and trenches, with mats sized accordingly; the set-up is checked before the first stroke.

    Owner: Temporary works coordinator / pump operator · Evidence: Set-up plan with ground bearing calc + pre-pour check

  • CP-02 · Concrete pumping & placement · Every pour

    Boom exclusion zone and overhead services

    Open

    The full boom slew radius is barricaded with the overhead power clearance confirmed; no work or parking under the boom path, and the operator has clear sight or a banksman with radio.

    Owner: Site supervisor · Evidence: Pump permit with radius plan and services check

  • CP-03 · Concrete pumping & placement · Every pour

    Line pump / pipeline restraint and blockage procedure

    Open

    Delivery lines are clamped and restrained at bends and risers; a written blockage-clearing procedure with pressure release and exclusion is briefed before the pour and followed if the line blocks.

    Owner: Pump contractor supervisor · Evidence: Pre-pour briefing record + line restraint check

  • CP-04 · Concrete pumping & placement · Every pour

    Formwork and falsework loading rate controlled

    Open

    Pour rate, drop height and sequence stay within the falsework designer's limits; a competent watchperson monitors props and ties throughout the pour with authority to stop.

    Owner: Temporary works coordinator · Evidence: Pour card with rate limit + watchperson log

  • CP-05 · Concrete pumping & placement · Every pour

    Washout, silica and skin exposure control

    Open

    Designated bunded washout is provided (no discharge to drains or ground); wet-concrete skin contact controls, eye wash and cutting/grinding dust suppression are in place for the crew.

    Owner: HSE officer / environmental officer · Evidence: Washout area photo, PPE issue, dust control record

  • FL-01 · Forklift & telehandler · On mobilisation + expiry tracking

    Operator licence, familiarisation and machine match

    Open

    Operator holds a current third-party licence for the class of machine, has documented site and machine familiarisation, and is not assigned to attachments they are not trained on.

    Owner: Plant coordinator · Evidence: Operator licence register + familiarisation record

  • FL-02 · Forklift & telehandler · Per task

    Load chart, attachments and telehandler as a crane

    Open

    The load chart for the fitted attachment is in the cab and used; when a telehandler lifts on hook or jib it is treated as a lifting operation with a lift plan and certified accessories.

    Owner: Lifting supervisor · Evidence: Load chart in cab, lift plan for suspended loads

  • FL-03 · Forklift & telehandler · Daily

    Pedestrian segregation and blind-corner control

    Open

    Traffic management gives pedestrians a physically separated route; blind corners have mirrors, banksmen or reduced speed, and reversing has an aid or spotter.

    Owner: Site logistics / traffic marshal · Evidence: Traffic management plan + daily walk check

  • FL-04 · Forklift & telehandler · Every shift

    Pre-use inspection and defect lock-out

    Open

    Documented pre-shift inspection covers tyres, forks/carriage, hydraulics, brakes, seatbelt, warning devices and load chart; defective machines are tagged out until repaired and re-checked.

    Owner: Operator / plant coordinator · Evidence: Pre-use checklist book + defect tag register

  • FL-05 · Forklift & telehandler · Per occurrence

    No riding, no man-cage without approval

    Open

    Personnel are never carried on forks or loads; work platforms on a telehandler are only used with a manufacturer-approved cage, integrated controls and a written justification that no safer access exists.

    Owner: Site supervisor · Evidence: Approved cage certificate + task justification

Entries are stored in this browser only — export the CSV or print for the project record.

Next step

Turn this into evidence you can hand over

Replace scattered spreadsheets and WhatsApp threads with one HSE operations system built around UAE authority expectations.

  • Built around UAE authoritiesADOSH-SF, Trakhees, DM, DCD, MOIAT and ISO 45001 structures.
  • Usable the same dayTemplates and registers are pre-filled with your company details.
  • Evidence, not just formsEvery record carries dates, signatures and an export you can hand over.