How to register for ADOSH-SF — step by step

In Abu Dhabi, companies enter ADOSH-SF through their Sector Regulatory Authority. This guide follows ADPHC Mechanism 3.0 — Identification, Assessment and Nomination of Entities (Version 4.0, 15 July 2024). Registering an individual safety practitioner is a separate process — see the practitioner registration guide.

  1. 1

    Find your Sector Regulatory Authority (SRA)

    Entities are not registered directly by ADPHC. Each entity is nominated or notified by the SRA relevant to its primary licence; where there are other licences or activities, the SRA that best fits the main activity applies.

    Mechanism 3.0 §2.2

  2. 2

    Describe your main operations on Form A1

    The SRA identifies entities using ADOSH-SF Form A1 — Identification of Entity Main Operations. Where operations span sectors, the SRA raises it with ADPHC with a completed Form A1, and ADPHC confirms the sector.

    Mechanism 3.0 §2.2.1

  3. 3

    Risk classification and nomination

    The SRA classifies the entity's risk using an ADPHC-approved process and submits proposed nominations to ADPHC for approval before informing the entity. ADPHC's decision on nomination is final.

    Mechanism 3.0 §2.3–2.5

  4. 4

    High-risk entities: complete Form A within 30 days

    The SRA officially informs a high-risk entity and gives it ADOSH-SF Form A (Registration for OSHMS Development). The entity completes Form A and registers with the SRA within the timescale the SRA sets — no longer than 30 calendar days. Use Form B later to update your details or development timelines.

    Mechanism 3.0 §2.7.1

  5. 5

    Start incident notification straight away

    Incident notification and reporting must start immediately following nomination/registration, under Mechanism 11.0.

    Mechanism 3.0 §2.8(c)(iv)

  6. 6

    Develop and submit your OSH management system

    The SRA sets a development deadline — a maximum of 12 months from the official nomination date for high-risk entities, and it may be shorter. The SRA monitors progress until the OSHMS is submitted and approved.

    Mechanism 3.0 §2.8(c)(i), §2.9

  7. 7

    After approval: implement, report and audit

    Start implementation within one month of SRA approval, start performance reporting in the next quarter, and complete the annual third-party audit within one year of OSHMS approval. ADPHC publishes the names of entities with an approved OSHMS.

    Mechanism 3.0 §2.8(c)(ii)–(v), §2.10

Medium-risk entities

Medium-risk entities are notified rather than nominated, and must comply with Mechanism 5.0 — OSH Requirements for Medium Risk Entities within a maximum of 6 months of notification. The SRA inspects within 6 months of notification, then at least once every three years (§2.7.2, §2.8(d)).

Official sources

  • ADPHC Mechanism 3.0 v4.0 (PDF)
  • Forms A, A1 and B are on ADPHC's ADOSH-SF Standard Forms page. Your SRA may also have its own submission route — confirm with them before submitting.

This guide summarises the official mechanism and is not legal advice or registration approval. Checked against the ADPHC document on 3 November 2026.

Get your ADOSH-SF records ready from day one

Incident reporting starts the moment you're nominated. Site Safety UAE keeps incidents, inspections, permits and training records referenced to ADOSH-SF — start free on one site.

Next step

Turn this into evidence you can hand over

Replace scattered spreadsheets and WhatsApp threads with one HSE operations system built around UAE authority expectations.

  • Built around UAE authoritiesADOSH-SF, Trakhees, DM, DCD, MOIAT and ISO 45001 structures.
  • Usable the same dayTemplates and registers are pre-filled with your company details.
  • Evidence, not just formsEvery record carries dates, signatures and an export you can hand over.