Site Operations

Crane Operations Safety

Safe lifting operations on UAE construction sites — crane selection, lift plans, competencies, exclusion zones, tandem lifts, weather limits and adjacent-crane clash management.

10 min
Video
10
Quiz questions
8 / 10
Pass threshold
0%
Your progress

Learning Objectives

  • Select the right crane and configuration for the lift.
  • Author and approve a lift plan and method statement.
  • Verify appointed person, lift supervisor, operator, slinger and banksman competencies.
  • Enforce exclusion zones, taglines and wind-limit stop rules.
  • Manage tandem lifts and adjacent-crane clash risks.

Training Video

Pro

Preview

10-minute video

Unlock this training video

The first 3 modules are free. Upgrade to Pro to watch every module, save progress, and issue certificates.

Upgrade to Pro

Module Content

1. Crane Selection

Mobile, crawler, tower, luffing or telehandler — chosen based on load weight, radius, height, ground bearing, and site constraints. Never lift beyond the load chart at the required radius; add margins for wind, dynamic effects and rigging weight.

2. Lift Plan & Method Statement

Every lift ≥ 90 % of SWL, tandem lift, or lift over live works requires a written lift plan authored by the Appointed Person (AP): load details, rigging, ground assessment, exclusion zones, communication, emergency response. Approved before mobilisation.

3. Competency Chain

Appointed Person (LEEA/CPCS/UAE MOL recognised), Lift Supervisor, Crane Operator (third-party certified — DM/Trakhees for the emirate), Slinger/Signaller, Banksman. All valid certificates on file; no informal role-swapping.

4. Exclusion Zones, Taglines & Weather

Full radius exclusion zone — no persons under any part of the load path. Taglines for controlling loads. Stop lifts above manufacturer wind limit (typically 9.8 m/s for mobiles, tower-specific for tower cranes); watch for gusts, not average wind. Sandstorm/lightning — stop.

5. Tandem Lifts & Crane Clashes

Two-crane lifts require dual lift plan, matched load monitoring, and one lead signaller. Adjacent cranes: zone-limitation systems (anti-collision), agreed slew envelopes, priority rules in the crane radio protocol. Never assume the other operator sees you.

6. UAE Requirements

DM Construction Safety CoP 4, Trakhees CoP, ADOSH-SF CoP 22 on lifting operations. Third-party inspection every 6 months (LEEA/TPI), daily pre-use check by operator, and monthly by AP. Incident reporting mandatory for any dropped load, near-miss or crane collision.

Knowledge Assessment

1. A written lift plan is mandatory for lifts:

2. The Appointed Person's role is:

3. Third-party crane inspection is required every:

4. Wind stop-limit for mobile cranes is typically:

5. Persons under the load path are:

6. Taglines are used to:

7. For adjacent tower cranes you should:

8. Crane operator certification in Dubai is administered by:

9. Tandem lifts require:

10. A dropped load or crane collision must be:

Certificate

Pass the quiz (8 / 10) to unlock your certificate.

Acknowledgement

By signing below, you confirm you have watched the training video, understood the material, and will apply these controls on site.

Complete the video and pass the quiz (8 / 10) to unlock signing.