Our safety management approach covers every area a consultant or client audit expects to see. It is built around three 100-point checklists — a weekly master site inspection, a hazard identification and review, and a corrective action close-out — aligned with UAE OSH frameworks (Dubai Municipality, ADOSH-SF, MOHRE and Civil Defence). Each point is verified on site with a yes / no / not-applicable answer, photo evidence and comments.
This policy is aligned with UAE frameworks but is not certified by any authority. Each site confirms the points against its own permits, risk assessments and method statements.
Master site inspection — 100 points
Run weekly on every site — the ten areas below, ten points each.
1. Documentation & permits
- Current HSE plan approved and available on site
- Site-specific risk assessments signed and in date
- Method statements approved for all active activities
- Permit-to-work register up to date, no expired permits active
- …and 6 more points
2. Site access, security & traffic
- Perimeter hoarding intact with no gaps or damage
- Gate controlled with sign-in register or access cards
- Visitors inducted and issued PPE before entry
- Traffic management plan in place and followed
- …and 6 more points
3. Housekeeping & welfare
- Walkways and access routes clear of materials and debris
- Waste segregated into marked skips and removed regularly
- Materials stacked safely and within height limits
- Drinking water available, cool and clean at all work areas
- …and 6 more points
4. Heat stress & health
- Midday break observed during the summer ban period
- Heat stress index monitored and recorded
- Work-rest cycles adjusted to heat level
- Electrolytes / ORS available to workers
- …and 6 more points
5. Work at height
- Scaffolds tagged and inspected within the last 7 days
- Guardrails, mid-rails and toe boards on all open edges
- Floor openings covered, secured and marked
- Harnesses inspected and anchored to rated points
- …and 6 more points
6. Excavation & confined spaces
- Excavation permit issued and valid
- Underground services located and marked before digging
- Sides shored, battered or stepped per depth
- Barriers and signs around all excavations
- …and 6 more points
7. Lifting operations & plant
- Lifting plan approved for each lift
- Crane third-party certificate valid
- Lifting accessories colour-coded and in date
- Operators and riggers hold valid certificates
- …and 6 more points
8. Electrical safety
- Distribution boards locked, labelled and IP-rated
- RCD / ELCB protection tested and recorded
- Cables routed overhead or protected, not in water
- Portable tools tested and tagged
- …and 6 more points
9. Fire & emergency
- Fire extinguishers present, accessible and inspected
- Hot work permits and fire watch in place
- Flammables stored in approved cabinets away from ignition
- Emergency exits and routes clear and signed
- …and 6 more points
10. PPE, chemicals & environment
- All workers wearing hard hats, boots and hi-vis
- Task-specific PPE (gloves, goggles, masks) used
- PPE stock available and damaged PPE replaced
- Chemical inventory and SDS available on site
- …and 6 more points
Master hazard identification & review — 100 points
A structured review of every hazard group, ending with verification of the controls in place.
1. Review scope & method
- Review scope, area and activities defined
- Review team includes supervisor, HSE and worker representative
- Previous hazard register reviewed
- Recent incidents and near misses considered
- …and 6 more points
2. Physical hazards
- Falls from height assessed
- Falling objects assessed
- Slips, trips and uneven ground assessed
- Noise exposure assessed
- …and 6 more points
3. Mechanical & plant hazards
- Moving plant and vehicle strike assessed
- Crane and lifting failures assessed
- Entanglement with rotating parts assessed
- Crushing / pinch points assessed
- …and 6 more points
4. Electrical & energy hazards
- Contact with live conductors assessed
- Overhead power lines assessed
- Buried cables assessed
- Temporary electrical installations assessed
- …and 6 more points
5. Fire & explosion hazards
- Hot work ignition sources assessed
- Flammable liquids and gases storage assessed
- Gas cylinder handling assessed
- Combustible waste accumulation assessed
- …and 6 more points
6. Chemical & biological hazards
- Hazardous substances inventory reviewed
- Silica and cement dust assessed
- Paints, solvents and adhesives assessed
- Asbestos or hazardous materials in existing structures assessed
- …and 6 more points
7. Ground & structural hazards
- Excavation collapse assessed
- Groundwater and flooding assessed
- Adjacent structures and undermining assessed
- Temporary works and formwork failure assessed
- …and 6 more points
8. Ergonomic & human-factor hazards
- Manual handling of heavy loads assessed
- Repetitive tasks and awkward postures assessed
- Fatigue and long shifts assessed
- Language and communication barriers assessed
- …and 6 more points
9. Environmental & public hazards
- Dust to neighbours and public assessed
- Noise to neighbours and out-of-hours work assessed
- Waste disposal and chain of custody assessed
- Water discharge and dewatering assessed
- …and 6 more points
10. Controls verification
- Each high risk has an engineering or elimination control
- Administrative controls documented in method statements
- PPE specified for residual risk
- Controls communicated in toolbox talks
- …and 6 more points
Master corrective action close-out — 100 points
Every finding is tracked from capture to verified close-out, with overdue follow-up and lessons learned.
1. Finding capture
- Finding clearly described with location
- Photo evidence of the finding attached
- Source recorded (inspection, audit, incident, client)
- Date and time of finding recorded
- …and 6 more points
2. Immediate containment
- Unsafe work stopped where required
- Area barricaded or isolated
- Affected equipment tagged out
- Workers informed of the hazard
- …and 6 more points
3. Root cause analysis
- Investigation lead appointed
- Witnesses interviewed
- Documents and permits reviewed
- Root cause method applied (5 Whys / fishbone)
- …and 6 more points
4. Action planning
- Corrective action addresses the root cause
- Preventive action to stop recurrence defined
- Action owner named
- Target date set and realistic
- …and 6 more points
5. Implementation
- Action started by the target start date
- Method statement or RA updated
- Procedures revised where needed
- Equipment repaired or replaced
- …and 6 more points
6. Evidence of completion
- Photo of completed action attached
- Before and after comparison available
- Updated documents attached
- Training attendance sheet attached
- …and 6 more points
7. Verification & effectiveness
- HSE verified the action in the field
- Verification date recorded
- Risk re-scored after the action
- Residual risk acceptable
- …and 6 more points
8. Overdue & escalation
- Overdue actions flagged in red
- Owner reminded before the due date
- Overdue actions escalated to the project manager
- Repeat overdue actions escalated to management
- …and 6 more points
9. Learning & sharing
- Lesson learned written up
- Lesson shared with other sites
- Hazard register updated
- Standard procedures updated
- …and 6 more points
10. Register management & close-out
- Register reviewed at the weekly HSE meeting
- Open vs closed counts reported
- Average close-out time tracked
- Actions grouped by category for trend analysis
- …and 6 more points
How it is used
- • Inspections, hazard reviews and actions are scheduled per site with due dates.
- • Owners and site managers are emailed before items fall due and when they go overdue.
- • Every point can carry photo proof; filled checklists stay private to the workspace and site.
- • Nothing is shared between users — each company's records are its own.
Next step
Turn this into evidence you can hand over
Replace scattered spreadsheets and WhatsApp threads with one HSE operations system built around UAE authority expectations.
- Built around UAE authoritiesADOSH-SF, Trakhees, DM, DCD, MOIAT and ISO 45001 structures.
- Usable the same dayTemplates and registers are pre-filled with your company details.
- Evidence, not just formsEvery record carries dates, signatures and an export you can hand over.