Part L — Registers & Records
Scaffold Inspection Checklist
Owner
HSE Manager / Document Controller
Review / trigger
Annual review; update on legal, authority, project or client change
Checkpoints
87
Writing or reviewing the risk assessment behind this checklist? Read the MSRA meaning in safety — Method Statement Risk Assessment guide for the full definition, UAE regulations, roles and scoring method.
| # | Area | Checkpoint / Requirement | Evidence / Acceptance Criteria | Responsible | Frequency |
|---|---|---|---|---|---|
| 1 | Erection Sequence Control | Erection sequence follows step-by-step method statement lift-by-lift without skipping bracing stages | Erection sequence log signed off per lift completed | Scaffold Supervisor | During erection |
| 2 | Erection Sequence Control | Partially erected scaffold left overnight is secured and stabilized against unauthorized use | End-of-shift stabilization check recorded | Scaffold Supervisor | Daily during erection |
| 3 | Scaffold Type Specific - Tube & Fitting | Tube and fitting scaffold couplers checked for correct torque using calibrated torque wrench | Torque wrench calibration certificate and sample readings logged | Scaffold Inspector | Weekly |
| 4 | Scaffold Type Specific - System Scaffold | System scaffold (cuplock/kwikstage) locking pins/wedges fully engaged at every node point | Node point sample check confirms full engagement | Scaffold Inspector | Weekly |
| 5 | Scaffold Type Specific - Mobile Tower | Mobile tower scaffold outriggers deployed and locked when height-to-base ratio requires stabilization | Outrigger deployment verified against manufacturer height chart | Scaffold Inspector | Before each use |
| 6 | Scaffold Type Specific - Suspended Scaffold | Suspended/swing stage scaffold wire ropes, hoists and counterweights inspected and load-tested before use | Load test certificate and wire rope inspection record | Scaffold Inspector | Before use and monthly |
| 7 | Scaffold Type Specific - Cantilever/Bracket | Cantilever or bracket scaffold anchorage into structure verified by engineer for load capacity | Engineer sign-off on bracket anchorage design and installation | Site Engineer | Before erection |
| 8 | Proximity Hazards | Scaffold erected near overhead power lines maintains statutory safe clearance distance | Clearance distance measured and documented against DEWA/utility regulations | HSE Officer | Before erection |
| 9 | Proximity Hazards | Scaffold adjacent to public roadway/walkway fitted with fan/hoarding to protect pedestrians | Protective fan/hoarding installation inspected and signed off | Site Supervisor | Before erection |
| 10 | Proximity Hazards | Scaffold near excavation maintains stable setback distance from excavation edge per geotechnical advice | Setback distance verified against excavation support drawing | Site Engineer | Before erection |
| 11 | Material Handling on Scaffold | Material hoist/gin wheel attachment point independently rated and not attached to working platform structure | Hoist attachment design verified separate from scaffold structure | Site Engineer | Before use |
| 12 | Material Handling on Scaffold | Materials raised/lowered on scaffold via designated loading bay only, not thrown or dropped | Loading bay location signed and used per observation | Site Supervisor | Daily |
| 13 | Public & Third-Party Protection | Scaffold sheeting/debris netting inspected for wear from wind/UV exposure over extended project duration | Netting condition assessed against degradation checklist | Scaffold Inspector | Monthly |
| 14 | Public & Third-Party Protection | Warning lights/beacons installed on scaffold sections adjacent to vehicular traffic routes at night | Beacon function check confirmed operational after dusk | Site Supervisor | Daily during night works |
| 15 | Independent Scaffold Sections | Independent scaffold (not tied to structure) has adequate base width-to-height ratio or additional ties/outriggers | Stability calculation or outrigger provision verified against height | Site Engineer | Before erection |
| 16 | Birdcage & Internal Scaffold | Birdcage scaffold internal bracing provides stability in all directions without external tie reliance | Internal bracing pattern matches design for enclosed scaffold type | Scaffold Inspector | Weekly |
| 17 | Scaffold Modification Control | Any request to remove/alter scaffold components routed through permit-to-modify process | Scaffold modification permit signed by scaffold supervisor and engineer if structural | Scaffold Supervisor | Per modification request |
| 18 | Scaffold Modification Control | Unauthorized modifications discovered during inspection immediately reported and rectified | Incident/observation report with rectification confirmation | Scaffold Inspector | As discovered |
| 19 | Tag System Detail | Scaffold tag holder legible, weatherproof and positioned at eye level at each access point | Tag holder condition and placement checked during walk-round | Scaffold Supervisor | Weekly |
| 20 | Tag System Detail | Scaffold tag reflects current inspector name, date of inspection and next due date without alteration | Tag entries compared against master inspection register for consistency | HSE Manager | Weekly |
| 21 | Statutory & Regulatory Compliance | Scaffold erection notified to relevant municipality/authority where required by local regulation | Notification/permit copy retained on site file | HSE Manager | Before erection |
| 22 | Statutory & Regulatory Compliance | Scaffold complies with OSHAD/Dubai Municipality temporary structure requirements applicable to emirate | Compliance checklist cross-referenced to local authority code | HSE Manager | Before erection |
| 23 | Interface with Other Trades | Scaffold access coordinated with concurrent works (e.g., crane lifts, façade works) to avoid conflict | Interface coordination meeting minutes documenting scaffold access windows | Site Supervisor | Weekly |
| 24 | Interface with Other Trades | Scaffold platform kept clear of unrelated trade materials not authorized for that work area | Housekeeping check confirms only authorized materials present | Site Supervisor | Daily |
| 25 | Scaffold at Height - Additional Controls | Scaffold above 6m fitted with additional intermediate tie level per design requirement | Tie level spacing verified against height-based design table | Scaffold Inspector | Weekly |
| 26 | Scaffold at Height - Additional Controls | Anemometer or wind monitoring device installed for scaffolds above defined height threshold | Wind speed data log reviewed against suspension threshold | Site Supervisor | Daily |
| 27 | Emergency Preparedness | Emergency evacuation route from elevated scaffold platform identified and kept clear | Evacuation route signage and clearance verified | HSE Officer | Weekly |
| 28 | Emergency Preparedness | First aid and rescue arrangements available for personnel working at scaffold height | Rescue plan specific to scaffold work posted at site | HSE Manager | Before work commencement |
| 29 | Photographic Evidence | Photographic record taken at each formal inspection showing overall scaffold condition and key details | Photo log attached to inspection register entry | Scaffold Inspector | Weekly |
| 30 | Photographic Evidence | Before/after photos retained for any scaffold alteration or repair | Photo comparison filed with modification permit | Scaffold Supervisor | Per modification |
| 31 | Training & Toolbox Talks | Toolbox talk delivered to all scaffold users on safe use, load limits and reporting defects | Toolbox talk attendance register with topic and date | Site Supervisor | Monthly |
| 32 | Training & Toolbox Talks | Scaffold inspectors hold current CISRS (or equivalent) inspection qualification | Qualification certificate verified and renewal date tracked | HSE Manager | On appointment and renewal |
| 33 | Subcontractor Scaffold Control | Subcontractor-erected scaffold subject to same inspection regime as main contractor scaffold | Subcontractor scaffold register reviewed during site audit | HSE Manager | Weekly |
| 34 | Subcontractor Scaffold Control | Scaffold handover between erecting contractor and using trades documented with joint walk-down | Joint handover checklist signed by both parties | Scaffold Supervisor | On handover |
| 35 | Weather-Specific Additional Checks | Scaffold inspected for ice/frost hazard on platforms and ladders in cold conditions | Cold weather inspection checklist completed where applicable | Scaffold Inspector | As required in cold weather |
| 36 | Weather-Specific Additional Checks | Scaffold checked for sand/dust accumulation on platforms affecting footing traction in desert conditions | Platform cleaning log confirms sand removal after dust events | Site Supervisor | After sandstorm event |
| 37 | Load Test & Verification | Loading class capacity verified by sample load calculation matching maximum anticipated material storage | Load calculation cross-checked against site material delivery plan | Site Engineer | Before heavy loading activity |
| 38 | Load Test & Verification | Concentrated point loads (e.g., stacked block pallets) assessed separately from uniform load rating | Point load assessment documented for specific heavy items | Site Engineer | Before placing point loads |
| 39 | Non-Conformance & Escalation | Critical scaffold non-conformance (structural instability) triggers immediate stop-work and evacuation | Stop-work notice issued and area evacuated with log entry | HSE Manager | Immediate on discovery |
| 40 | Non-Conformance & Escalation | Recurring non-conformances trigger review of scaffolding contractor's competency and retraining | Contractor performance review record with corrective action plan | HSE Manager | As trend identified |
| 41 | Digital Inspection Records | Scaffold inspection conducted using digital checklist app with GPS/photo timestamp verification | Digital inspection record with timestamp and geolocation metadata | Scaffold Inspector | Weekly |
| 42 | Digital Inspection Records | Digital scaffold inspection data synced to central HSE dashboard for real-time status visibility | Dashboard record matches field inspection within 24 hours | HSE Manager | Weekly |
| 43 | Final Handback & Demobilization | Scaffold materials counted and reconciled against delivery record upon demobilization | Material reconciliation report with variance explanation | Scaffold Supervisor | On demobilization |
| 44 | Final Handback & Demobilization | Area beneath and around dismantled scaffold inspected and reinstated (ground reinstatement, debris removal) | Area handover inspection checklist confirms reinstatement complete | Site Supervisor | After dismantling |
| 45 | Insurance & Liability Documentation | Scaffold contractor's insurance/liability coverage verified as current before erection commences | Insurance certificate validity checked against project dates | Procurement Officer | Before mobilization |
| 46 | Insurance & Liability Documentation | Incident involving scaffold reported to insurer within required notification period | Incident notification correspondence with insurer on file | HSE Manager | As occurs |
| 47 | Bird Nesting & Pest Control | Scaffold sheeting/cavities checked for bird nesting or pest infestation affecting structural cleanliness | Pest inspection checklist completed for long-duration scaffolds | Scaffold Inspector | Monthly |
| 48 | Design & Competency | Scaffold erected/altered/dismantled only by trained and certified scaffolders | Scaffolder training/competency cards checked and verified | Scaffold Supervisor | Before assignment |
| 49 | Design & Competency | Complex or non-standard scaffold design approved by competent engineer per TG20/BS EN 12811 | Engineered design drawing on file matching erected configuration | Site Engineer | Before erection |
| 50 | Design & Competency | Scaffold design accounts for wind loading, loading class and working platform configuration | Design calculation includes wind load and platform load class | Design Engineer | Before erection |
| 51 | Design & Competency | Method statement and risk assessment specific to scaffold erection/dismantling approved | Signed MS/RA on site with supervisor briefing record | Scaffold Supervisor | Before erection |
| 52 | Foundation & Base Support | Base plates and sole boards used on all standards to distribute load evenly | Sole board size/thickness checked against ground bearing capacity | Scaffold Supervisor | Before erection |
| 53 | Foundation & Base Support | Scaffold founded on firm, level ground free of voids, ice or excessive slope | Ground condition inspected and recorded before erection | Scaffold Supervisor | Before erection |
| 54 | Foundation & Base Support | Adjustable base jacks extended within permissible limit per manufacturer instructions | Jack extension measured against maximum allowable thread exposure | Scaffold Inspector | Before erection |
| 55 | Structural Integrity | Standards vertical within tolerance and spaced per design/loading class | Standard spacing and verticality measured with level/plumb line | Scaffold Inspector | Weekly |
| 56 | Structural Integrity | Ledgers and transoms level and correctly coupled at every lift | Coupler check confirms correct type and torque at each junction | Scaffold Inspector | Weekly |
| 57 | Structural Integrity | Bracing (facade, ledger and plan bracing) installed per design pattern for structural stability | Bracing configuration matches approved scaffold drawing | Scaffold Inspector | Weekly |
| 58 | Structural Integrity | Ties to permanent structure installed at required vertical/horizontal spacing and rated capacity | Tie pattern and pull/push test results recorded | Scaffold Inspector | Weekly |
| 59 | Structural Integrity | Couplers (right-angle, swivel, sleeve) are load-rated, undamaged and correctly tightened | Torque check log for sample of couplers | Scaffold Inspector | Weekly |
| 60 | Structural Integrity | No unauthorized alterations, tube removal or overloading of scaffold structure since last inspection | Comparison against last inspection tag/photo record | Scaffold Inspector | Weekly |
| 61 | Working Platforms | Platform boards fully boarded (no gaps) and free of splits, warping or excessive deflection | Board condition and coverage visually verified across full platform width | Scaffold Inspector | Weekly |
| 62 | Working Platforms | Platform boards secured against uplift/movement with board clips or tied down | Board clip/tie inspection confirms no loose boards | Scaffold Inspector | Weekly |
| 63 | Working Platforms | Working platform width adequate for task and material storage per loading class | Platform width measured against design/loading class requirement | Scaffold Inspector | Weekly |
| 64 | Working Platforms | Platform load not exceeding designated loading class rating (light/medium/heavy duty) | Load estimation checked against posted loading class signage | Site Supervisor | Daily |
| 65 | Edge Protection & Access | Guardrails installed at minimum 950mm (top rail) with mid-rail at all open edges | Guardrail height measured and confirmed at all platform edges | Scaffold Inspector | Weekly |
| 66 | Edge Protection & Access | Toe boards minimum 150mm installed at all platform edges to prevent falling objects | Toe board height and continuity verified around platform perimeter | Scaffold Inspector | Weekly |
| 67 | Edge Protection & Access | Access ladders/stair towers secured, extending min 1m above landing point with safe access | Ladder tie-off and extension height measured | Scaffold Inspector | Weekly |
| 68 | Edge Protection & Access | Internal access points (ladder bay) fitted with trapdoor/hatch or staggered access to prevent falls | Access hatch mechanism functional and self-closing where required | Scaffold Inspector | Weekly |
| 69 | Edge Protection & Access | Debris netting/sheeting installed and secured where required to prevent falling material hazards | Netting fixed at all edges with no gaps or tears | Scaffold Inspector | Weekly |
| 70 | Tagging & Signage | Scaffold tag (Scafftag/equivalent) displayed at all access points showing inspection status | Green tag current within 7-day validity, or red tag for do-not-use status | Scaffold Inspector | Weekly |
| 71 | Tagging & Signage | Incomplete scaffold clearly identified with red/do-not-use tag and physical barrier at access | Barrier tape/physical block installed with incomplete scaffold signage | Scaffold Supervisor | During erection |
| 72 | Tagging & Signage | Loading class signage posted and visible at scaffold access points | Signage matches design loading class in kN/m2 | Scaffold Supervisor | On completion |
| 73 | Formal Inspection Regime | Scaffold formally inspected by competent person before first use after erection | Handover inspection certificate signed before use | Scaffold Inspector | Before first use |
| 74 | Formal Inspection Regime | Scaffold re-inspected after any alteration, adverse weather event or incident | Re-inspection record dated to event trigger | Scaffold Inspector | After alteration/weather event |
| 75 | Formal Inspection Regime | Routine scaffold inspection conducted and documented at maximum 7-day intervals | Weekly inspection register with signature and findings | Scaffold Inspector | Every 7 days |
| 76 | Formal Inspection Regime | Inspection findings/non-conformances closed out before scaffold returned to service | NCR closure record referenced on inspection tag | Scaffold Inspector | As raised |
| 77 | Weather & Environmental | Scaffold use suspended during high wind conditions exceeding manufacturer/design limits | Wind speed monitoring log with suspension record | Site Supervisor | During adverse weather |
| 78 | Weather & Environmental | Sheeting/netting removed or secured additionally ahead of forecast high wind events | Weather forecast review and preventive action log | Scaffold Supervisor | Before forecast event |
| 79 | Weather & Environmental | Scaffold inspected for ground settlement/washout after heavy rainfall | Post-rain inspection checklist completed | Scaffold Inspector | After rainfall event |
| 80 | Loading & Usage Control | Materials on platform distributed evenly and not stacked against guardrails | Material placement observed during daily walk-round | Site Supervisor | Daily |
| 81 | Loading & Usage Control | Mobile/tower scaffold castors locked before use and never moved while occupied | Castor lock check before each work session | User / Site Supervisor | Before each use |
| 82 | Loading & Usage Control | Scaffold not used to support hoists, rubbish chutes or external loads unless specifically designed | Design verification for any attached equipment | Site Engineer | Before attachment |
| 83 | Dismantling | Dismantling sequence follows reverse erection method statement to maintain stability | Dismantling sequence checklist signed off by supervisor | Scaffold Supervisor | During dismantling |
| 84 | Dismantling | Exclusion zone and barricading established below dismantling area | Barricade/signage inspected before dismantling starts | Site Supervisor | Before dismantling |
| 85 | Dismantling | Dismantled components inspected, sorted and stored for reuse or condemned if damaged | Component condition log updated post-dismantling | Scaffold Supervisor | After dismantling |
| 86 | Documentation & Records | Scaffold inspection register maintained on site covering full erection-to-dismantling lifecycle | Register available for audit with continuous entries | Scaffold Supervisor | Ongoing |
| 87 | Documentation & Records | Handover certificate issued to end user/trade confirming scaffold fit for intended use | Signed handover certificate referencing loading class and configuration | Scaffold Supervisor | On handover |
Each checkpoint records Status (Yes / No / N/A), Comments, Corrective Action and Sign-off. Switch to Complete in-app to fill it here, or download the blank version to complete on site.
Next step
Turn this into evidence you can hand over
Replace scattered spreadsheets and WhatsApp threads with one HSE operations system built around UAE authority expectations.
- Built around UAE authoritiesADOSH-SF, Trakhees, DM, DCD, MOIAT and ISO 45001 structures.
- Usable the same dayTemplates and registers are pre-filled with your company details.
- Evidence, not just formsEvery record carries dates, signatures and an export you can hand over.