Part H — High-Risk Works
Hot work permit checklist
Workbook section 81
Owner
HSE Manager / Document Controller
Review / trigger
Annual review; update immediately if legal, authority, project, client, or scope requirements change.
Primary references
Plan H81 Hot Work Fire Watch
Checkpoints
88
Writing or reviewing the risk assessment behind this checklist? Read the MSRA meaning in safety — Method Statement Risk Assessment guide for the full definition, UAE regulations, roles and scoring method.
| # | Area | Checkpoint / Requirement | Evidence / Acceptance Criteria | Responsible | Frequency |
|---|---|---|---|---|---|
| 1 | Pre-Job Site Survey | Hot work location surveyed jointly with fire watch to identify hidden fire spread paths through ducts, cavities and false ceilings | Survey checklist with sketch of concealed spaces near work area | HSE Officer | Before work |
| 2 | Pre-Job Site Survey | Sprinkler and fire detection systems in the work zone confirmed operational and not isolated unless formally impaired-permitted | Fire system status log confirming zone active or documented impairment permit | HSE Manager | Before work |
| 3 | Pre-Job Site Survey | Adjacent trades and occupants notified of hot work schedule to avoid conflicting activities in same fire zone | Notification record/email log to affected parties | Site Supervisor | Before work |
| 4 | Pre-Job Site Survey | Wind direction and outdoor hot work location assessed to prevent sparks drifting toward stored materials or public areas | Site observation log noting wind assessment outcome | HSE Officer | Per outdoor job |
| 5 | Weld Fume & Health Exposure | Local exhaust ventilation or fume extraction arms used for welding in enclosed areas to control fume exposure | Fume extraction equipment inspection and positioning record | HSE Officer | Per job |
| 6 | Weld Fume & Health Exposure | Respiratory protective equipment provided and fit-tested for welders exposed to fumes from galvanized or coated metals | Fit-test certificate matching worker and respirator model | HSE Officer | Per assignment |
| 7 | Weld Fume & Health Exposure | Occupational exposure monitoring for welding fume conducted periodically in enclosed work areas | Exposure monitoring report with results below OEL | HSE Manager | Quarterly |
| 8 | Barricading & Signage | Hot work zone cordoned with warning signage indicating active welding/cutting operations to nearby personnel | Signage photo showing 'Hot Work in Progress' warning at perimeter | Site Supervisor | Per job |
| 9 | Barricading & Signage | Screens erected to shield adjacent workers and public from arc flash and UV radiation exposure | Screen installation photo confirming full coverage of arc line of sight | HSE Officer | Per job |
| 10 | Electrical Safety for Welding Sets | Welding machine earthing and insulation resistance tested before deployment to site | Insulation resistance test certificate for welding set | HSE Officer | Per deployment |
| 11 | Electrical Safety for Welding Sets | Welding cables routed clear of walkways and water to prevent trip hazards and insulation damage | Site inspection photo showing cable routing and protection | Site Supervisor | Daily |
| 12 | Cylinder Storage & Handling | Oxygen and acetylene cylinders stored in separate, ventilated, fire-rated cages with segregation distance maintained | Cylinder storage inspection checklist confirming segregation | Store Keeper | Weekly |
| 13 | Cylinder Storage & Handling | Cylinder valves closed and regulators removed at end of each shift or when hot work is not in progress | End-of-shift equipment shutdown checklist signed by operator | Operator | Daily |
| 14 | Cylinder Storage & Handling | Cylinder colour coding and labelling verified legible to prevent gas misidentification | Visual inspection record confirming label and colour condition | HSE Officer | Weekly |
| 15 | Hot Work in Marine/Offshore Zones | Additional gas-free certificate obtained for hot work on tanks, pipelines or vessels previously containing flammable substances | Gas-free certificate issued by certified marine chemist | HSE Manager | Per job |
| 16 | Hot Work in Marine/Offshore Zones | Hot work near water bodies or drainage assessed for fuel/oil sheen risk before commencing | Pre-work water surface inspection log | HSE Officer | Before work |
| 17 | Subcontractor Hot Work Control | Subcontractor hot work crews inducted into main contractor permit system before independent permit issuance | Subcontractor induction record referencing permit procedure | HSE Officer | Per subcontractor mobilization |
| 18 | Subcontractor Hot Work Control | Subcontractor fire watch and equipment competency verified equivalent to main contractor standard before approval | Competency verification checklist for subcontractor crew | HSE Manager | Per subcontractor |
| 19 | Night Shift Hot Work | Adequate task lighting provided at night hot work locations to maintain fire watch visibility | Lux level measurement record at work location | Site Supervisor | Per night job |
| 20 | Night Shift Hot Work | Night shift permit issuer and fire watch contact details confirmed reachable by site security control room | Security control room log listing active night permits | HSE Officer | Per night shift |
| 21 | Waste & Slag Disposal | Hot slag and weld spatter collected in metal containers away from combustible waste bins | Photo evidence of dedicated non-combustible slag container in use | Site Supervisor | Per job |
| 22 | Waste & Slag Disposal | Cooling period enforced before disposal of hot work debris into general waste skips | Waste disposal log noting cooling time observed | HSE Officer | Per job |
| 23 | Interface with Other Permits | Hot work permit cross-checked against confined space, excavation and electrical permits active in same area to avoid conflict | Permit interface register showing cross-referenced active permits | HSE Manager | Per job |
| 24 | Interface with Other Permits | Simultaneous operations (SIMOPS) review conducted where hot work coincides with lifting or scaffolding activity nearby | SIMOPS review form signed by relevant supervisors | HSE Manager | Per occurrence |
| 25 | Weather & Environmental Controls | Outdoor hot work suspended during high wind conditions exceeding site-defined threshold near flammable stockpiles | Weather log with wind speed and suspension decision | Site Supervisor | Daily |
| 26 | Weather & Environmental Controls | Rain/moisture protection provided for electrical welding equipment during outdoor operations | Equipment weather protection inspection record | HSE Officer | Per outdoor job |
| 27 | Post-Work Verification | Area re-inspected by fire watch and supervisor jointly before permit closure to confirm no residual heat source | Joint post-work inspection sign-off on permit closure section | Site Supervisor | Per job |
| 28 | Post-Work Verification | Photographic record of work area taken at closure to document safe condition | Closure photo attached to permit file | HSE Officer | Per job |
| 29 | Management of Change | Change in hot work method, location or equipment triggers reassessment and re-issuance of permit rather than amendment | Change log referencing superseded and new permit numbers | HSE Manager | Per change |
| 30 | Contractor Equipment Certification | Third-party welding machines and gas equipment brought on site verified for valid inspection certification before use | Equipment certification check log at site gate | HSE Officer | Per equipment entry |
| 31 | Incident Learning & Sharing | Lessons learned from hot work near-misses shared across project sites via HSE bulletin | HSE bulletin distribution record referencing lesson learned | HSE Manager | Per occurrence |
| 32 | Incident Learning & Sharing | Hot work permit system periodically reviewed and updated based on audit findings and incident trends | Permit procedure revision log with review date and approver | HSE Manager | Annually |
| 33 | Permit Issuance | Hot work permit raised and approved by authorized issuer before any welding, cutting, grinding or brazing commences | Signed hot work permit displayed at work location prior to start | HSE Officer | Per job |
| 34 | Permit Issuance | Permit specifies exact task, location, equipment and validity period not exceeding single shift | Permit form with start/end time fields completed and matching shift roster | Permit Issuer | Per permit |
| 35 | Permit Issuance | Permit cross-referenced to approved method statement and risk assessment for the specific hot work task | RAMS reference number recorded on permit face | HSE Officer | Per permit |
| 36 | Permit Issuance | Civil Defence NOC/approval obtained where hot work is within notifiable proximity of fire alarm zones or occupied buildings | Dubai Civil Defence NOC letter attached to permit file | HSE Manager | Per project phase |
| 37 | Permit Issuance | Permit renewal required if work extends beyond original validity, with re-inspection of area before renewal | Renewed permit bearing new time-stamp and re-inspection signature | Permit Issuer | Per renewal |
| 38 | Permit Issuance | Permit immediately suspended and physically retrieved if conditions change (e.g., gas leak alarm, wind change for outdoor works) | Suspended permit marked 'VOID' with reason and time noted | HSE Officer | As required |
| 39 | Permit Issuance | Copy of active permit retained at site HSE office and duplicate posted at work location | Two permit copies verified during site walk | HSE Officer | Per permit |
| 40 | Permit Issuance | Permit issuer holds valid competency/authorization record for issuing hot work permits | Training/authorization certificate on file for named issuer | HSE Manager | Annually |
| 41 | Permit Issuance | Closed permit signed off by issuer confirming area left in safe condition after work completion | Permit closure section signed and dated | Permit Issuer | Per job |
| 42 | Permit Issuance | Permit register maintained logging all issued, active, suspended and closed permits with unique numbering | Sequential permit register with no gaps in numbering | HSE Officer | Daily |
| 43 | Permit Issuance | Multiple simultaneous hot work permits within same fire zone reviewed jointly to prevent compounded fire risk | Joint risk review note attached when more than one permit active in a zone | HSE Manager | Per occurrence |
| 44 | Gas Testing & Atmosphere | Combustible gas/atmosphere test conducted before hot work in confined or enclosed spaces | Gas test log showing LEL reading below 10 percent before entry | HSE Officer | Before entry |
| 45 | Gas Testing & Atmosphere | Gas testing equipment calibrated per manufacturer schedule and calibration certificate available on site | Current calibration certificate matching instrument serial number | HSE Officer | Per calibration cycle |
| 46 | Gas Testing & Atmosphere | Continuous atmospheric monitoring maintained throughout hot work in confined spaces with alarm set points defined | Monitoring log/data sheet showing readings at set intervals | Standby Person | Continuous during work |
| 47 | Gas Testing & Atmosphere | Ventilation provided and verified adequate before and during hot work in enclosed areas | Ventilation equipment operating log and airflow verification record | Site Supervisor | Per job |
| 48 | Gas Testing & Atmosphere | Gas test results recorded on permit with tester name, time and reading value | Permit gas-test section fully completed and signed | HSE Officer | Per test |
| 49 | Gas Testing & Atmosphere | Re-testing performed if work is interrupted for more than 30 minutes or personnel exit and re-enter | Repeat gas test entry logged with new timestamp | HSE Officer | Per interruption |
| 50 | Gas Testing & Atmosphere | Oxygen level verified within 19.5 to 23.5 percent range before confined space hot work entry | Gas test log showing oxygen percentage within acceptable range | HSE Officer | Before entry |
| 51 | Fire Watch & Extinguishing | Dedicated fire watch personnel assigned and present throughout hot work and for minimum 30 minutes after completion | Fire watch log signed with start and post-work end time | Fire Watch Officer | Per job |
| 52 | Fire Watch & Extinguishing | Fire watch personnel trained in use of appropriate extinguisher type for materials present at location | Fire watch training certificate on file | HSE Manager | Annually |
| 53 | Fire Watch & Extinguishing | Minimum two serviceable fire extinguishers of correct class positioned within immediate reach of hot work location | Extinguisher inspection tag current and physical count verified | Fire Watch Officer | Per job |
| 54 | Fire Watch & Extinguishing | Fire watch has no other concurrent duties that could distract from continuous fire monitoring | Site roster confirming fire watch as sole assigned task | Site Supervisor | Per job |
| 55 | Fire Watch & Extinguishing | Fire hose reel or standpipe connection accessible and tested where hot work occurs near high fire-load areas | Hose reel inspection tag current, pressure test record available | HSE Officer | Per project phase |
| 56 | Fire Watch & Extinguishing | Emergency contact numbers for Civil Defence and site fire response team posted at hot work location | Posted emergency contact card visible at site | HSE Officer | Per job |
| 57 | Fire Watch & Extinguishing | Fire watch log includes periodic area checks for smouldering material up to one hour post-completion for high-risk tasks | Post-work inspection log with timed entries up to 60 minutes | Fire Watch Officer | Per job |
| 58 | Combustible Material Control | Combustible and flammable materials removed or relocated minimum 11 meters from hot work location where practicable | Pre-work area clearance checklist confirming distance measured | HSE Officer | Before work |
| 59 | Combustible Material Control | Materials that cannot be removed are covered with fire-resistant blankets or shields | Photo evidence of fire blanket placement over fixed combustibles | Site Supervisor | Before work |
| 60 | Combustible Material Control | Floor openings, wall penetrations and gaps sealed to prevent sparks falling to lower or adjacent areas | Inspection record confirming openings sealed prior to work start | HSE Officer | Before work |
| 61 | Combustible Material Control | Housekeeping of hot work area maintained free of oil, grease, sawdust and packaging debris | Area inspection checklist marked clear of debris | Site Supervisor | Daily |
| 62 | Combustible Material Control | Fire-resistant screens or curtains erected to contain sparks when working at height or near open edges | Screen installation verified during pre-work inspection | HSE Officer | Per job |
| 63 | Combustible Material Control | Gas cylinders and flammable liquid containers stored minimum required distance from hot work in ventilated area | Storage inspection log confirming segregation distance | Store Keeper | Weekly |
| 64 | Equipment & PPE | Welding/cutting equipment inspected for damaged cables, hoses, regulators and connections before use | Pre-use equipment inspection checklist signed by operator | Operator | Before each use |
| 65 | Equipment & PPE | Gas cylinders secured upright, valves protected and flashback arrestors fitted on both oxygen and fuel gas lines | Visual inspection confirming flashback arrestors installed at cylinder and torch ends | HSE Officer | Per job |
| 66 | Equipment & PPE | Operator wears appropriate PPE including welding shield/goggles, fire-resistant gloves and flame-retardant clothing | PPE inspection checklist and toolbox talk attendance record | Site Supervisor | Per job |
| 67 | Equipment & PPE | Earthing/grounding of welding return cable verified to prevent stray arcing | Continuity test record for earth return connection | HSE Officer | Per setup |
| 68 | Equipment & PPE | Electrical hot work equipment tested and tagged per PAT/inspection schedule before deployment | Current PAT tag visible on equipment | HSE Officer | Per test cycle |
| 69 | Equipment & PPE | Gas cylinder trolleys used for transport and cylinders never dragged, rolled or dropped | Site observation record noting compliant handling practice | Site Supervisor | Ongoing |
| 70 | Confined Space Hot Work | Confined space entry permit issued jointly with hot work permit where hot work occurs inside confined space | Cross-referenced permit numbers on both documents | HSE Officer | Per entry |
| 71 | Confined Space Hot Work | Rescue plan and standby rescue team in place before confined space hot work commences | Rescue plan document with named standby team on permit | HSE Manager | Per entry |
| 72 | Confined Space Hot Work | Communication method between entrant and standby person established and tested before entry | Communication check log signed before entry | Standby Person | Per entry |
| 73 | Confined Space Hot Work | Forced ventilation maintained throughout confined space hot work with fume extraction at source | Ventilation equipment running log throughout job duration | Site Supervisor | Continuous during work |
| 74 | Confined Space Hot Work | Number of personnel and entry/exit times logged on confined space entry board | Entry board with names, in-time and out-time recorded | Standby Person | Per entry |
| 75 | Training & Competency | All hot work operators hold valid trade competency certification for welding/cutting equipment used | Competency certificate matching operator name and equipment type | HSE Manager | Annually |
| 76 | Training & Competency | Toolbox talk on hot work hazards conducted before task and attendance recorded | Toolbox talk attendance sheet dated and signed | Site Supervisor | Per job |
| 77 | Training & Competency | Fire watch personnel receive refresher training annually covering extinguisher use and escalation procedure | Refresher training record dated within past 12 months | HSE Manager | Annually |
| 78 | Training & Competency | New workers undergo hot work induction covering permit system before assignment to hot work tasks | Induction record signed by new worker and inductor | HSE Officer | Per new worker |
| 79 | Emergency Preparedness | Emergency evacuation route from hot work location identified and kept clear at all times | Route marked on site emergency plan and physically verified clear | HSE Officer | Per job |
| 80 | Emergency Preparedness | Nearest fire alarm call point and assembly point location communicated to hot work team | Toolbox talk record referencing alarm point and assembly area | Site Supervisor | Per job |
| 81 | Emergency Preparedness | Fire incident response drill conducted periodically covering hot work fire scenario | Drill report with date, scenario and attendance list | HSE Manager | Semi-annually |
| 82 | Emergency Preparedness | Civil Defence liaison contact maintained and site emergency plan updated with current approvals | Updated emergency plan referencing valid Civil Defence approval number | HSE Manager | Annually |
| 83 | Emergency Preparedness | Post-incident review conducted for any fire event arising from hot work with corrective actions logged | Incident report with root cause and corrective action tracker | HSE Manager | Per incident |
| 84 | Audit & Documentation | Hot work permits archived for minimum 3 years for audit and insurance purposes | Document retention log confirming 3-year archive period | HSE Manager | Ongoing |
| 85 | Audit & Documentation | Monthly audit of closed hot work permits conducted to verify compliance with fire watch and gas test requirements | Audit checklist with sampled permit references and findings | HSE Manager | Monthly |
| 86 | Audit & Documentation | Non-compliant hot work practices identified during audit escalated via corrective action register | CAPA reference number linked to audit finding | HSE Manager | Per audit |
| 87 | Audit & Documentation | Statistics on hot work permits issued, suspended and fire incidents reported in monthly HSE report | Monthly HSE report section with hot work statistics | HSE Manager | Monthly |
| 88 | Audit & Documentation | Subcontractor hot work permit compliance reviewed as part of subcontractor HSE performance evaluation | Subcontractor evaluation form with hot work compliance score | HSE Manager | Monthly |
Each checkpoint records Status (Yes / No / N/A), Comments, Corrective Action and Sign-off. Switch to Complete in-app to fill it here, or download the blank version to complete on site.
Next step
Turn this into evidence you can hand over
Replace scattered spreadsheets and WhatsApp threads with one HSE operations system built around UAE authority expectations.
- Built around UAE authoritiesADOSH-SF, Trakhees, DM, DCD, MOIAT and ISO 45001 structures.
- Usable the same dayTemplates and registers are pre-filled with your company details.
- Evidence, not just formsEvery record carries dates, signatures and an export you can hand over.