Part H — High-Risk Works

Demolition / strip-out

Workbook section 88
Owner
HSE Manager / Document Controller
Review / trigger
Annual review; update immediately if legal, authority, project, client, or scope requirements change.
Primary references
Plans TOC - Part H; H - Demolition Strip-Out Contro; Plan H88 Demolition Dismantling
Checkpoints
88

Writing or reviewing the risk assessment behind this checklist? Read the MSRA meaning in safety — Method Statement Risk Assessment guide for the full definition, UAE regulations, roles and scoring method.

Open live checklist
#AreaCheckpoint / RequirementEvidence / Acceptance CriteriaResponsibleFrequency
1Pre-Demolition Survey & PermitsStructural survey and demolition method statement approved prior to mobilizationInspection record / checklist / sign-off confirming compliance with the above requirementSite EngineerDaily
2Pre-Demolition Survey & PermitsAsbestos/hazardous material survey completed and certified by licensed surveyorInspection record / checklist / sign-off confirming compliance with the above requirementHSE OfficerBefore each use
3Pre-Demolition Survey & PermitsDemolition permit obtained from municipality/authority (e.g. Dubai Municipality, Trakhees)Inspection record / checklist / sign-off confirming compliance with the above requirementTemporary Works CoordinatorWeekly
4Pre-Demolition Survey & PermitsUtility disconnection certificates obtained (electricity, water, gas, telecom)Inspection record / checklist / sign-off confirming compliance with the above requirementStructural EngineerPer pour/activity
5Pre-Demolition Survey & PermitsAdjacent building condition survey and photographic record completedInspection record / checklist / sign-off confirming compliance with the above requirementSite SupervisorOnce (pre-start)
6Pre-Demolition Survey & PermitsTraffic management plan approved where demolition affects public roadsInspection record / checklist / sign-off confirming compliance with the above requirementProject ManagerPer shift
7Pre-Demolition Survey & PermitsNotification to neighboring occupants/owners issued prior to worksInspection record / checklist / sign-off confirming compliance with the above requirementForemanMonthly
8Pre-Demolition Survey & PermitsThird-party insurance and liability cover confirmed valid for demolition scopeInspection record / checklist / sign-off confirming compliance with the above requirementSafety OfficerAs required
9Pre-Demolition Survey & PermitsFire and safety authority approval obtained where applicable for demolition scopeInspection record / checklist / sign-off confirming compliance with the above requirementSite EngineerDaily
10Pre-Demolition Survey & PermitsInsurance of surrounding assets confirmed before commencing worksInspection record / checklist / sign-off confirming compliance with the above requirementHSE OfficerBefore each use
11Pre-Demolition Survey & PermitsEnvironmental impact assessment reviewed for demolition dust and noiseInspection record / checklist / sign-off confirming compliance with the above requirementTemporary Works CoordinatorWeekly
12Site Preparation & IsolationSite hoarding and demolition warning signage erected around perimeterInspection record / checklist / sign-off confirming compliance with the above requirementStructural EngineerPer pour/activity
13Site Preparation & IsolationExclusion zone established and barricaded with controlled access pointsInspection record / checklist / sign-off confirming compliance with the above requirementSite SupervisorOnce (pre-start)
14Site Preparation & IsolationAll services capped, isolated and tagged prior to strip-out commencementInspection record / checklist / sign-off confirming compliance with the above requirementProject ManagerPer shift
15Site Preparation & IsolationFire hydrants and firefighting access maintained clear during worksInspection record / checklist / sign-off confirming compliance with the above requirementForemanMonthly
16Site Preparation & IsolationDust suppression system (water spray/misting) installed and testedInspection record / checklist / sign-off confirming compliance with the above requirementSafety OfficerAs required
17Site Preparation & IsolationSite lighting provided for demolition activities conducted in low lightInspection record / checklist / sign-off confirming compliance with the above requirementSite EngineerDaily
18Site Preparation & IsolationEmergency evacuation route identified and kept clear of debrisInspection record / checklist / sign-off confirming compliance with the above requirementHSE OfficerBefore each use
19Site Preparation & IsolationWelfare facilities relocated clear of demolition drop zoneInspection record / checklist / sign-off confirming compliance with the above requirementTemporary Works CoordinatorWeekly
20Site Preparation & IsolationOverhead and underground utility drawings verified before excavation/breakingInspection record / checklist / sign-off confirming compliance with the above requirementStructural EngineerPer pour/activity
21Site Preparation & IsolationPedestrian walkway diversions signed and clearly markedInspection record / checklist / sign-off confirming compliance with the above requirementSite SupervisorOnce (pre-start)
22Site Preparation & IsolationCCTV surveillance installed to monitor exclusion zone complianceInspection record / checklist / sign-off confirming compliance with the above requirementProject ManagerPer shift
23Strip-Out Sequence & MethodSoft-strip sequence follows approved method statement top-down orderInspection record / checklist / sign-off confirming compliance with the above requirementForemanMonthly
24Strip-Out Sequence & MethodNon-structural partitions and finishes removed before structural elementsInspection record / checklist / sign-off confirming compliance with the above requirementSafety OfficerAs required
25Strip-Out Sequence & MethodMEP first fix items disconnected and removed prior to ceiling strip-outInspection record / checklist / sign-off confirming compliance with the above requirementSite EngineerDaily
26Strip-Out Sequence & MethodGlazing and curtain wall panels removed using certified lifting equipmentInspection record / checklist / sign-off confirming compliance with the above requirementHSE OfficerBefore each use
27Strip-Out Sequence & MethodFloor finishes and screed removal sequenced to avoid slab overloadInspection record / checklist / sign-off confirming compliance with the above requirementTemporary Works CoordinatorWeekly
28Strip-Out Sequence & MethodSalvageable materials identified, tagged and stored for reuse/recyclingInspection record / checklist / sign-off confirming compliance with the above requirementStructural EngineerPer pour/activity
29Strip-Out Sequence & MethodDemolition of structural elements only after engineer's sequence approvalInspection record / checklist / sign-off confirming compliance with the above requirementSite SupervisorOnce (pre-start)
30Strip-Out Sequence & MethodControlled demolition technique verified against structural stability calculationsInspection record / checklist / sign-off confirming compliance with the above requirementProject ManagerPer shift
31Strip-Out Sequence & MethodVibration monitoring conducted where sensitive equipment/structures are nearbyInspection record / checklist / sign-off confirming compliance with the above requirementForemanMonthly
32Strip-Out Sequence & MethodCutting and coring works assessed for structural impact before executionInspection record / checklist / sign-off confirming compliance with the above requirementSafety OfficerAs required
33Strip-Out Sequence & MethodSequential removal of services coordinated with strip-out scheduleInspection record / checklist / sign-off confirming compliance with the above requirementSite EngineerDaily
34Plant, Equipment & MachineryExcavators/breakers inspected with valid third-party certificationInspection record / checklist / sign-off confirming compliance with the above requirementHSE OfficerBefore each use
35Plant, Equipment & MachineryOperators hold valid competency licence for demolition plant operatedInspection record / checklist / sign-off confirming compliance with the above requirementTemporary Works CoordinatorWeekly
36Plant, Equipment & MachineryDaily pre-use checklist completed for all demolition machineryInspection record / checklist / sign-off confirming compliance with the above requirementStructural EngineerPer pour/activity
37Plant, Equipment & MachineryLong-reach demolition equipment stability confirmed on working platformInspection record / checklist / sign-off confirming compliance with the above requirementSite SupervisorOnce (pre-start)
38Plant, Equipment & MachineryLifting appliances used for debris removal certified and load testedInspection record / checklist / sign-off confirming compliance with the above requirementProject ManagerPer shift
39Plant, Equipment & MachineryPlant exclusion zones enforced with banksman/spotter deployedInspection record / checklist / sign-off confirming compliance with the above requirementForemanMonthly
40Plant, Equipment & MachineryReversing alarms and CCTV functional on all demolition vehiclesInspection record / checklist / sign-off confirming compliance with the above requirementSafety OfficerAs required
41Plant, Equipment & MachineryFuel storage and refuelling areas bunded and away from ignition sourcesInspection record / checklist / sign-off confirming compliance with the above requirementSite EngineerDaily
42Plant, Equipment & MachineryLifting plan prepared for heavy demolition component removalInspection record / checklist / sign-off confirming compliance with the above requirementHSE OfficerBefore each use
43Plant, Equipment & MachineryMachine maintenance records reviewed prior to mobilization to siteInspection record / checklist / sign-off confirming compliance with the above requirementTemporary Works CoordinatorWeekly
44Plant, Equipment & MachineryNoise and emission levels of plant checked against permitted limitsInspection record / checklist / sign-off confirming compliance with the above requirementStructural EngineerPer pour/activity
45Structural Stability & Temporary SupportTemporary propping/shoring installed prior to removal of load-bearing elementsInspection record / checklist / sign-off confirming compliance with the above requirementSite SupervisorOnce (pre-start)
46Structural Stability & Temporary SupportStructural engineer sign-off obtained for partial demolition sequencingInspection record / checklist / sign-off confirming compliance with the above requirementProject ManagerPer shift
47Structural Stability & Temporary SupportMonitoring points installed on adjacent structures for movement/vibrationInspection record / checklist / sign-off confirming compliance with the above requirementForemanMonthly
48Structural Stability & Temporary SupportProgressive collapse risk assessed and control measures implementedInspection record / checklist / sign-off confirming compliance with the above requirementSafety OfficerAs required
49Structural Stability & Temporary SupportRetained structure stability verified after each demolition phaseInspection record / checklist / sign-off confirming compliance with the above requirementSite EngineerDaily
50Structural Stability & Temporary SupportDeflection and crack monitoring instruments checked and logged dailyInspection record / checklist / sign-off confirming compliance with the above requirementHSE OfficerBefore each use
51Structural Stability & Temporary SupportTemporary works design register updated for all demolition supportsInspection record / checklist / sign-off confirming compliance with the above requirementTemporary Works CoordinatorWeekly
52Structural Stability & Temporary SupportLoad path verification completed before removing supporting columns/wallsInspection record / checklist / sign-off confirming compliance with the above requirementStructural EngineerPer pour/activity
53Structural Stability & Temporary SupportTemporary works removal sequence agreed with design engineerInspection record / checklist / sign-off confirming compliance with the above requirementSite SupervisorOnce (pre-start)
54Structural Stability & Temporary SupportBracing adequacy re-verified after each partial demolition stageInspection record / checklist / sign-off confirming compliance with the above requirementProject ManagerPer shift
55Structural Stability & Temporary SupportContingency plan established for unexpected structural instabilityInspection record / checklist / sign-off confirming compliance with the above requirementForemanMonthly
56Hazardous Materials ManagementAsbestos containing materials removed only by licensed specialist contractorInspection record / checklist / sign-off confirming compliance with the above requirementSafety OfficerAs required
57Hazardous Materials ManagementAir monitoring conducted during and after asbestos removal worksInspection record / checklist / sign-off confirming compliance with the above requirementSite EngineerDaily
58Hazardous Materials ManagementHazardous waste segregated, labelled and stored in designated areaInspection record / checklist / sign-off confirming compliance with the above requirementHSE OfficerBefore each use
59Hazardous Materials ManagementLead paint and other hazardous coatings handled per safe work procedureInspection record / checklist / sign-off confirming compliance with the above requirementTemporary Works CoordinatorWeekly
60Hazardous Materials ManagementPPE for hazardous material handling verified as per material safety data sheetInspection record / checklist / sign-off confirming compliance with the above requirementStructural EngineerPer pour/activity
61Hazardous Materials ManagementDecontamination unit provided for personnel exiting hazardous work zonesInspection record / checklist / sign-off confirming compliance with the above requirementSite SupervisorOnce (pre-start)
62Hazardous Materials ManagementWaste transfer notes and manifests completed for hazardous material disposalInspection record / checklist / sign-off confirming compliance with the above requirementProject ManagerPer shift
63Hazardous Materials ManagementChemical/gas cylinders removed and disposed of before structural demolitionInspection record / checklist / sign-off confirming compliance with the above requirementForemanMonthly
64Hazardous Materials ManagementMercury/PCB containing equipment identified and removed by specialistsInspection record / checklist / sign-off confirming compliance with the above requirementSafety OfficerAs required
65Hazardous Materials ManagementHazardous material removal certificates obtained before general demolitionInspection record / checklist / sign-off confirming compliance with the above requirementSite EngineerDaily
66Hazardous Materials ManagementSpill kits available at hazardous material handling locationsInspection record / checklist / sign-off confirming compliance with the above requirementHSE OfficerBefore each use
67Debris Management & HousekeepingDebris chutes or controlled drop zones used for upper floor material removalInspection record / checklist / sign-off confirming compliance with the above requirementTemporary Works CoordinatorWeekly
68Debris Management & HousekeepingDaily housekeeping schedule maintained to prevent debris accumulationInspection record / checklist / sign-off confirming compliance with the above requirementStructural EngineerPer pour/activity
69Debris Management & HousekeepingSegregated waste skips provided for concrete, metal, wood and general wasteInspection record / checklist / sign-off confirming compliance with the above requirementSite SupervisorOnce (pre-start)
70Debris Management & HousekeepingRecycling targets tracked and reported per project waste management planInspection record / checklist / sign-off confirming compliance with the above requirementProject ManagerPer shift
71Debris Management & HousekeepingDebris removal vehicles covered/sheeted to prevent spillage on public roadsInspection record / checklist / sign-off confirming compliance with the above requirementForemanMonthly
72Debris Management & HousekeepingWheel washing facility provided at site exit to prevent road contaminationInspection record / checklist / sign-off confirming compliance with the above requirementSafety OfficerAs required
73Debris Management & HousekeepingNoise levels monitored and kept within permitted limits during debris handlingInspection record / checklist / sign-off confirming compliance with the above requirementSite EngineerDaily
74Debris Management & HousekeepingStockpile heights and locations controlled to avoid overloading structuresInspection record / checklist / sign-off confirming compliance with the above requirementHSE OfficerBefore each use
75Debris Management & HousekeepingWeighbridge/waste tracking records maintained for disposal verificationInspection record / checklist / sign-off confirming compliance with the above requirementTemporary Works CoordinatorWeekly
76Debris Management & HousekeepingDebris removal route agreed with traffic authority where requiredInspection record / checklist / sign-off confirming compliance with the above requirementStructural EngineerPer pour/activity
77Debris Management & HousekeepingEnd-of-shift housekeeping inspection conducted and recordedInspection record / checklist / sign-off confirming compliance with the above requirementSite SupervisorOnce (pre-start)
78PPE, Training & Emergency PreparednessTask-specific PPE (helmet, goggles, gloves, respirator) issued and wornInspection record / checklist / sign-off confirming compliance with the above requirementProject ManagerPer shift
79PPE, Training & Emergency PreparednessToolbox talk conducted daily covering specific demolition hazardsInspection record / checklist / sign-off confirming compliance with the above requirementForemanMonthly
80PPE, Training & Emergency PreparednessEmergency response plan rehearsed for structural collapse scenarioInspection record / checklist / sign-off confirming compliance with the above requirementSafety OfficerAs required
81PPE, Training & Emergency PreparednessFirst aiders and fire wardens assigned and available on demolition shiftInspection record / checklist / sign-off confirming compliance with the above requirementSite EngineerDaily
82PPE, Training & Emergency PreparednessConfined space entry procedures followed for below-grade demolition worksInspection record / checklist / sign-off confirming compliance with the above requirementHSE OfficerBefore each use
83PPE, Training & Emergency PreparednessWorking at height controls verified for elevated strip-out activitiesInspection record / checklist / sign-off confirming compliance with the above requirementTemporary Works CoordinatorWeekly
84PPE, Training & Emergency PreparednessManual handling training provided for debris clearance personnelInspection record / checklist / sign-off confirming compliance with the above requirementStructural EngineerPer pour/activity
85PPE, Training & Emergency PreparednessEmergency contact numbers and muster point displayed at site entranceInspection record / checklist / sign-off confirming compliance with the above requirementSite SupervisorOnce (pre-start)
86PPE, Training & Emergency PreparednessCompetency verification conducted for demolition supervisors and operatorsInspection record / checklist / sign-off confirming compliance with the above requirementProject ManagerPer shift
87PPE, Training & Emergency PreparednessRescue plan established for personnel trapped under debris scenarioInspection record / checklist / sign-off confirming compliance with the above requirementForemanMonthly
88PPE, Training & Emergency PreparednessInduction training records verified for all demolition workforceInspection record / checklist / sign-off confirming compliance with the above requirementSafety OfficerAs required

Each checkpoint records Status (Yes / No / N/A), Comments, Corrective Action and Sign-off. Switch to Complete in-app to fill it here, or download the blank version to complete on site.

Next step

Turn this into evidence you can hand over

Replace scattered spreadsheets and WhatsApp threads with one HSE operations system built around UAE authority expectations.

  • Built around UAE authoritiesADOSH-SF, Trakhees, DM, DCD, MOIAT and ISO 45001 structures.
  • Usable the same dayTemplates and registers are pre-filled with your company details.
  • Evidence, not just formsEvery record carries dates, signatures and an export you can hand over.