Part G — Equipment & Plant

MEWP safety

Workbook section 65
Owner
HSE Manager / Document Controller
Review / trigger
Annual review; update immediately if legal, authority, project, client, or scope requirements change.
Primary references
Plans TOC - Part G; Plan G65 MEWP Boom Lift Scissor
Checkpoints
89
Open live checklist
#AreaCheckpoint / RequirementEvidence / Acceptance CriteriaResponsibleFrequency
1Selection and SuitabilityCorrect MEWP type/category selected for task height, reach and terrainEquipment selection matrix reviewed against task requirements and site surveySite SupervisorBefore task
2Selection and SuitabilityMachine capacity verified sufficient for combined weight of operators, tools and materialsLoad calculation checked against platform rated capacityMEWP OperatorBefore task
3Selection and SuitabilityAlternative access methods considered and MEWP justified as safest optionHierarchy of access control documented in RAMSHSE OfficerBefore task
4Pre-Mobilisation InspectionSupplier delivery inspection compared against hire agreement condition reportCondition report signed by both parties, discrepancies notedSite SupervisorOn delivery
5Pre-Mobilisation InspectionNon-conforming or expired-certificate units rejected at point of deliveryRejection notice issued to supplier, unit not accepted onto siteHSE OfficerOn delivery
6Operational PlanningExclusion zone dimensions calculated based on boom outreach and fall radiusExclusion zone plan drawn and approved before setupSite SupervisorBefore task
7Operational PlanningTask duration and battery/fuel capacity matched to planned work periodCharge/fuel level checked against estimated task durationMEWP OperatorBefore task
8Operational PlanningMultiple MEWP operation coordinated to avoid boom collisionCoordination plan/radio protocol established for simultaneous operationSite SupervisorBefore task
9Setup and PositioningOutriggers deployed on load-spreading pads on soft or uneven groundPads sized per manufacturer spec, placement verified before elevationMEWP OperatorBefore task
10Setup and PositioningMachine levelled within manufacturer tolerance before platform is raisedBubble level/onboard indicator checked, within toleranceMEWP OperatorBefore task
11Setup and PositioningAdequate clearance maintained from building edges, scaffolding and fixed structuresClearance distances measured and confirmed against method statementMEWP OperatorBefore task
12Rescue and Emergency ResponseRescue equipment (secondary MEWP, ladder, descent device) available on siteRescue equipment identified in rescue plan and physically presentSite SupervisorBefore task
13Rescue and Emergency ResponseRescue team members trained and roles assigned prior to task startRescue roles briefed and acknowledged in toolbox talkSite SupervisorBefore task
14Rescue and Emergency ResponseEmergency contact numbers and rescue plan location communicated to all crewRescue plan posted at work area, contact numbers verified currentHSE OfficerBefore task
15Rescue and Emergency ResponseSuspension trauma awareness briefed to harness-wearing operatorsToolbox talk record covering suspension trauma symptoms and responseHSE OfficerBefore task
16Loading and Material HandlingMaterials secured on platform to prevent falling objectsTools/materials tethered or contained, tool lanyards usedMEWP OperatorEvery use
17Loading and Material HandlingPlatform load evenly distributed and within rated capacity at all timesLoad distribution checked visually and against capacity plateMEWP OperatorEvery use
18Loading and Material HandlingNo unauthorized modifications (extension platforms, ladders) used on MEWPVisual inspection confirms only manufacturer-approved attachments in useHSE OfficerEvery use
19Traffic and Pedestrian ManagementSegregation maintained between MEWP operating zone and pedestrian routesBarriers/signage inspected, pedestrian diversion route signedBanksmanBefore task
20Traffic and Pedestrian ManagementVehicle movements near MEWP controlled by banksman with clear line of sightBanksman positioned with unobstructed view, high-visibility clothing wornBanksmanContinuous
21Fall Protection SystemsGuardrail system inspected for compliance with fall protection standard prior to elevationGuardrail height and toe board confirmed compliant before useMEWP OperatorDaily
22Fall Protection SystemsFall arrest lanyard length limits free fall distance appropriately for boom-type unitsLanyard length verified against platform height and manufacturer guidanceMEWP OperatorEvery use
23Night and Low-Visibility OperationsAdequate lighting provided for MEWP operation during night shiftsLux level survey confirms sufficient illumination of work areaSite SupervisorBefore night task
24Night and Low-Visibility OperationsMachine fitted with working headlights and platform floodlight where used at nightFunction test of lighting equipment prior to shift startMEWP OperatorBefore night task
25Weather and Environmental MonitoringAnemometer calibrated and mounted at appropriate height for accurate wind readingsCalibration certificate current, mounting position verifiedHSE OfficerMonthly
26Weather and Environmental MonitoringHeat stress precautions applied for operators during peak summer hoursMidday work ban compliance confirmed, hydration breaks scheduledHSE OfficerDaily (summer)
27Incident and Near-Miss ManagementMEWP-related incidents and near-misses reported through site HSE systemIncident report submitted within required timeframe with root cause analysisHSE OfficerAs needed
28Incident and Near-Miss ManagementLessons learned from MEWP incidents communicated to all operatorsToolbox talk or bulletin issued summarizing corrective actionsHSE ManagerAs needed
29End of Task ProceduresPlatform lowered fully and boom stowed in travel position before leaving unattendedVisual confirmation of stowed position and parking brake engagedMEWP OperatorEnd of shift
30End of Task ProceduresPost-use inspection completed and defects logged before handover to next shiftHandover checklist signed off with defect status notedMEWP OperatorEnd of shift
31Insurance and Contractual ComplianceThird-party liability insurance for MEWP operation valid and covers task scopeInsurance certificate reviewed against task risk profileHSE ManagerBefore mobilisation
32Pre-Use DocumentationValid third-party thorough examination certificate (LOLER-equivalent) in date for the MEWPCertificate displayed/available in cab, expiry not exceeded 6 months (or 12 months per manufacturer/ADOSH-SF)HSE OfficerBefore use
33Pre-Use DocumentationDaily pre-use inspection checklist completed by trained operatorSigned daily checklist on file, no outstanding defectsMEWP OperatorDaily
34Pre-Use DocumentationMachine-specific Rescue Plan available on siteWritten rescue plan referencing this MEWP model, reviewed by supervisorSite SupervisorBefore use
35Pre-Use DocumentationIPAF/ADOSH-SF operator license and photo ID validLicense card checked against machine category (1a/1b/3a/3b)IPAF OperatorBefore use
36Pre-Use DocumentationFamiliarisation/handover record for rental/transferred unitSigned familiarisation form from supplier for this specific unitSite SupervisorOn mobilisation
37Pre-Use DocumentationRisk assessment and method statement (RAMS) specific to MEWP task approvedApproved RAMS on site referencing ground conditions, exclusion zone, overhead hazardsHSE OfficerBefore task
38Operator CompetencyMEWP operator holds valid IPAF PAL card for category in usePAL card category matches boom/scissor type being operatedIPAF OperatorBefore use
39Operator CompetencyOperator has received site-specific inductionSigned induction register including MEWP hazardsSite SupervisorOnce per site
40Operator CompetencyGround personnel/banksman trained in MEWP exclusion zone controlTraining record for banksman duties around MEWPSite SupervisorBefore task
41Operator CompetencyOperator fit for work (no fatigue, medication, alcohol)Fit-to-work declaration signed dailyMEWP OperatorDaily
42Operator CompetencyRefresher training completed if license expired >12 months since last useRefresher training certificate on fileHSE OfficerAs required
43Machine Structural ConditionChassis, boom sections and scissor arms free of cracks, dents or corrosionVisual inspection log, no structural damage notedMEWP OperatorDaily
44Machine Structural ConditionGuardrails, mid-rails and toe boards intact on platformPlatform enclosure complete to 1.1m minimum heightMEWP OperatorDaily
45Machine Structural ConditionPlatform gate/chain self-closing and latching correctlyGate closes and latches under own weight, tested manuallyMEWP OperatorDaily
46Machine Structural ConditionOutriggers/stabilizers free of damage and fully extend/retractFunction test performed, pins and locks engage fullyMEWP OperatorDaily
47Machine Structural ConditionTyres/tracks in serviceable condition with correct pressureTyre pressure per manufacturer spec, no visible damage or wear beyond limitMEWP OperatorDaily
48Machine Structural ConditionLoad chart/capacity plate legible and fitted to machineCapacity plate present, matches configuration, all text readableMEWP OperatorDaily
49Controls and Safety DevicesEmergency lowering/descent system tested and functionalManual descent valve operated during pre-use check, works within spec timeMEWP OperatorDaily
50Controls and Safety DevicesPlatform controls clearly labelled and functioning (drive, lift, slew)Function test of all controls performed at ground level before elevatingMEWP OperatorDaily
51Controls and Safety DevicesGround-level emergency stop/lowering controls operationalGround controls tested, override function confirmed workingMEWP OperatorDaily
52Controls and Safety DevicesTilt/level (inclinometer) alarm and cut-out functioningAlarm triggers and drive/lift cuts out when tilt threshold simulated/testedMEWP OperatorDaily
53Controls and Safety DevicesAudible reversing alarm and beacon operationalAlarm sounds on reverse travel, beacon flashes when poweredMEWP OperatorDaily
54Controls and Safety DevicesLoad sensing/overload cut-out system testedOverload alarm activates at rated capacity during function testMEWP OperatorWeekly
55Controls and Safety DevicesHorn functional for operator-to-ground communicationHorn audible test performedMEWP OperatorDaily
56Personal Protective EquipmentFull body harness with short lanyard worn in boom-type MEWPsHarness and lanyard inspected, anchor point used, tag-in date validMEWP OperatorDaily
57Personal Protective EquipmentHarness anchor point attached to designated anchorage in platformLanyard clipped to manufacturer-designated point, not guardrailMEWP OperatorEvery use
58Personal Protective EquipmentHard hat with chin strap worn on platformPPE inspection confirms chin strap fitted and usedMEWP OperatorEvery use
59Personal Protective EquipmentHigh-visibility vest worn by operator and ground personnelVisual confirmation during task briefingSite SupervisorEvery use
60Personal Protective EquipmentHarness webbing and stitching free from cuts, fraying or chemical damagePre-use harness inspection checklist completed, tag currentMEWP OperatorDaily
61Work Area and Ground ConditionsGround surface assessed as firm, level and capable of bearing MEWP loadGround bearing capacity assessment recorded for the task locationSite SupervisorBefore task
62Work Area and Ground ConditionsExclusion zone barriers and warning signage erected around MEWP footprintBarricades and signage in place per method statementBanksmanBefore task
63Work Area and Ground ConditionsOverhead hazards identified (power lines, structures, other plant)Overhead survey/permit reviewed, minimum approach distances maintainedSite SupervisorBefore task
64Work Area and Ground ConditionsUnderground/floor penetrations and slopes checked within operating limitsSlope/gradient measured against manufacturer's maximum permissible inclineMEWP OperatorBefore task
65Work Area and Ground ConditionsWind speed monitored and within manufacturer's operating limitAnemometer reading logged, work stopped above rated wind speedSite SupervisorContinuous
66Work Area and Ground ConditionsProximity to other MEWPs, cranes or moving vehicles controlledTraffic management plan referenced, spotters assigned where requiredSite SupervisorBefore task
67Electrical and Environmental HazardsMinimum safe approach distance to live power lines maintainedDistance verified against DEWA/ADDC clearance table for voltage classHSE OfficerBefore task
68Electrical and Environmental HazardsWeatherproofing checked before use in rain or high humidityMachine rated for weather conditions, electrical components sealedMEWP OperatorBefore task
69Electrical and Environmental HazardsBattery/fuel charging area ventilated and free of ignition sourcesCharging station inspected, no smoking/hot work signage postedHSE OfficerWeekly
70Electrical and Environmental HazardsTask not conducted during lightning/severe weather warningWeather advisory checked, work suspended per site severe weather procedureSite SupervisorContinuous
71Permits and CommunicationWork at height permit issued and signed for MEWP taskPermit reviewed and authorised prior to platform elevationSite SupervisorBefore task
72Permits and CommunicationTwo-way radio or communication method established between operator and groundRadio check completed, backup communication method identifiedMEWP OperatorBefore task
73Permits and CommunicationToolbox talk conducted covering MEWP hazards and rescue planToolbox talk register signed by all involved personnelSite SupervisorBefore task
74Permits and CommunicationPermit to work closed out and machine parked/secured after taskPermit closure signature, keys removed, machine chockedSite SupervisorAfter task
75Maintenance and RecordsScheduled maintenance per manufacturer service interval completedMaintenance log shows service hours/dates up to dateMaintenance TeamPer service schedule
76Maintenance and RecordsDefects reported during use logged and machine tagged out if unsafeDefect/near-miss log entry, 'Do Not Use' tag applied where requiredMEWP OperatorAs needed
77Maintenance and RecordsFuel/battery levels checked and refuelling/charging area compliantLog entry confirming adequate charge/fuel prior to shiftMEWP OperatorDaily
78Maintenance and RecordsThorough examination history retained and traceable to asset numberExamination records filed against unique MEWP asset/serial numberHSE OfficerOngoing
79Transport and MobilisationMEWP transported on suitable trailer/low-loader with load securedLoad securing checked against transport method statement, straps rated correctlyTransport SupervisorEach transport
80Transport and MobilisationPre-delivery inspection conducted by supplier and defects recorded before handoverSupplier delivery inspection report signed and filedSite SupervisorOn delivery
81Transport and MobilisationAccess route to work location surveyed for width, height and load-bearing clearanceRoute survey report confirms clearance for boom/scissor dimensionsSite SupervisorBefore mobilisation
82Transport and MobilisationMachine parked on stable ground with keys removed and isolated when not attendedIsolation switch/key removed, wheels chocked, area barricaded overnightMEWP OperatorEnd of shift
83Battery/Fuel and Power SystemsBattery terminals clean, secure and free of corrosion (electric MEWPs)Visual inspection of battery compartment during pre-use checkMEWP OperatorDaily
84Battery/Fuel and Power SystemsDiesel/LPG engine exhaust emissions checked for confined/indoor use suitabilityEmission rating checked, catalytic converter fitted if used indoorsHSE OfficerBefore indoor task
85Battery/Fuel and Power SystemsCharging cables and connectors inspected for damage before connectingVisual inspection of charger lead and plug prior to overnight chargingMEWP OperatorDaily
86Battery/Fuel and Power SystemsFuel/gas cylinders secured and leak-free (LPG-powered units)Leak test with soap solution/detector, cylinder strapped in bracketMEWP OperatorDaily
87Signage and MarkingMachine capacity, model and safe working load clearly marked and legibleDecals and safety signage inspected for legibilityMEWP OperatorDaily
88Signage and MarkingWarning decals for crush/entrapment hazard points intactDecals present at control panel and chassis pinch pointsMEWP OperatorWeekly
89Signage and MarkingUnique asset/fleet number displayed and matched to inspection registerAsset number visible on chassis and cross-checked against registerHSE OfficerWeekly

Each checkpoint records Status (Yes / No / N/A), Comments, Corrective Action and Sign-off. Switch to Complete in-app to fill it here, or download the blank version to complete on site.

Next step

Turn this into evidence you can hand over

Replace scattered spreadsheets and WhatsApp threads with one HSE operations system built around UAE authority expectations.

  • Built around UAE authoritiesADOSH-SF, Trakhees, DM, DCD, MOIAT and ISO 45001 structures.
  • Usable the same dayTemplates and registers are pre-filled with your company details.
  • Evidence, not just formsEvery record carries dates, signatures and an export you can hand over.