Part G — Equipment & Plant
Equipment inspection and colour coding
Workbook section 60
Owner
HSE Manager / Document Controller
Review / trigger
Annual review; update immediately if legal, authority, project, client, or scope requirements change.
Primary references
Plans TOC - Part G; Plan K125 Equipment Inspection ; E - Equipment Inspection Regist; Plan G60 Equipment Inspection C
Checkpoints
88
| # | Area | Checkpoint / Requirement | Evidence / Acceptance Criteria | Responsible | Frequency |
|---|---|---|---|---|---|
| 1 | Colour coding system administration | Colour code chart references cross-checked with civil defence and municipality guidance for the emirate of operation | Reference document attached to colour coding procedure | HSE Manager | Annually |
| 2 | Colour coding system administration | Newly mobilised equipment tagged with current colour immediately on arrival at site gate before entry to work areas | Gate inspection log with tag colour recorded | Security/HSE Officer | On arrival |
| 3 | Colour coding system administration | Colour coding audit conducted across all equipment yards to detect mismatched or missing tags | Audit checklist with equipment ID and tag status | HSE Officer | Monthly |
| 4 | Colour coding system administration | Handover of colour coding scheme to incoming shift/subcontractor HSE personnel documented | Shift handover log referencing colour scheme | HSE Officer | Weekly |
| 5 | Lifting equipment inspection (LOLER-style regime) | Register of lifting equipment includes unique identification number, SWL, manufacture date and last examination date | Register entry reviewed for completeness per item | HSE Manager | Monthly |
| 6 | Lifting equipment inspection (LOLER-style regime) | Wire rope slings inspected for broken wires, kinking and corrosion against discard criteria | Sling inspection checklist with discard criteria reference | Rigger | Weekly |
| 7 | Lifting equipment inspection (LOLER-style regime) | Below-the-hook lifting devices (spreader beams, lifting beams) load tested and certified before first use | Load test certificate on file | Third Party Inspector | Before first use |
| 8 | Lifting equipment inspection (LOLER-style regime) | Chain slings inspected for stretch, twisted links and damaged hooks with safety latches intact | Chain sling inspection checklist | Rigger | Weekly |
| 9 | Lifting equipment inspection (LOLER-style regime) | Competent person examination reports reviewed by HSE Manager and action items tracked to closure | Report review sign-off and action tracker | HSE Manager | Per examination |
| 10 | Mobile and tower crane inspection | Crane foundation/base design and ground bearing capacity verified by structural engineer before erection | Foundation design certificate and ground bearing test result | Structural Engineer | Before erection |
| 11 | Mobile and tower crane inspection | Mobile crane outrigger pads and ground conditions checked and confirmed adequate before each set-up | Ground bearing check recorded on lift plan | Crane Operator | Before each set-up |
| 12 | Mobile and tower crane inspection | Radio communication between crane operator, banksman and rigger tested functional before lift commences | Radio check log | Lifting Supervisor | Before each lift |
| 13 | Mobile and tower crane inspection | Tower crane tie-in/collar connections inspected and certified after each climbing operation | Tie-in inspection certificate | Lifting Engineer | Per climb |
| 14 | Mobile and tower crane inspection | Crane exclusion zone maintained beneath the slew radius with barricading and signage during operation | Exclusion zone inspection record | Banksman | Daily |
| 15 | Mobile and tower crane inspection | Multiple crane operations within overlapping working radii covered by an anti-collision procedure | Anti-collision procedure and radio protocol document | Lifting Supervisor | Before dual operations |
| 16 | Excavators, loaders and earthmoving equipment | Fire extinguisher mounted, accessible and within inspection date on all mobile plant | Extinguisher inspection tag check | Plant Operator | Monthly |
| 17 | Excavators, loaders and earthmoving equipment | Bucket teeth and cutting edges inspected for wear or looseness that could detach during operation | Inspection checklist item recorded | Plant Operator | Daily |
| 18 | Excavators, loaders and earthmoving equipment | Operator cabin glazing intact and mirrors clean, providing full visibility of work area | Visual inspection checklist | Plant Operator | Daily |
| 19 | Excavators, loaders and earthmoving equipment | Attachment quick-hitch coupler function-tested with visual confirmation of full engagement before each use | Coupler engagement test log | Plant Operator | Before each attachment change |
| 20 | Excavators, loaders and earthmoving equipment | Mobile plant excluded from proximity to overhead power lines unless safe clearance distance confirmed | Proximity permit / clearance distance record | Site Engineer | Before deployment |
| 21 | Excavators, loaders and earthmoving equipment | Refuelling of mobile plant conducted in designated bunded area with spill kit available | Refuelling area inspection and spill kit check | Plant Operator | Daily |
| 22 | Power tools and portable electrical equipment | Temporary distribution boards inspected for correct fusing, labelling and enclosure integrity | Distribution board inspection checklist | Electrical Supervisor | Weekly |
| 23 | Power tools and portable electrical equipment | Battery-operated cordless tools inspected for charger condition and battery casing damage before use | Pre-use inspection checklist | Worker | Daily |
| 24 | Power tools and portable electrical equipment | Circular saws and cut-off machines fitted with correctly rated blade guards prior to issue | Issue checklist with guard verification | Tool Store Keeper | Before issue |
| 25 | Power tools and portable electrical equipment | Voltage of power tools matched to site electrical supply (110V on construction sites where mandated) | Tool voltage rating check against site supply | Electrical Supervisor | Before issue |
| 26 | Scaffolding and access equipment | Scaffold base plates, sole boards and standards inspected for correct bearing on stable ground | Scaffold inspection checklist entry | Scaffold Inspector | Weekly |
| 27 | Scaffolding and access equipment | Working platforms fitted with toe boards, guardrails and mid-rails at all open edges | Edge protection inspection record | Scaffold Inspector | Weekly |
| 28 | Scaffolding and access equipment | Scaffold ties and bracing verified against approved scaffold design drawing | Design drawing cross-check during inspection | Scaffold Inspector | Weekly |
| 29 | Scaffolding and access equipment | Podium steps and platform ladders inspected for locking mechanism function and stability before use | Pre-use inspection checklist | User | Daily |
| 30 | Scaffolding and access equipment | Suspended/rope access equipment inspected and certified by competent person before deployment | Suspended access inspection certificate | Third Party Inspector | Before deployment |
| 31 | Pressure vessels, compressors and gas equipment | Compressor hoses and quick-release couplings secured with whip-check restraints | Whip-check installation inspection | HSE Officer | Weekly |
| 32 | Pressure vessels, compressors and gas equipment | Gas cylinder trolleys used for transport with cylinders chained upright during movement | Transport method observation | Worker | As required |
| 33 | Pressure vessels, compressors and gas equipment | Nitrogen and inert gas cylinders stored separately from flammable gas cylinders with clear signage | Storage segregation inspection | HSE Officer | Weekly |
| 34 | Pressure vessels, compressors and gas equipment | Compressor safety valve set pressure verified against vessel design pressure during statutory inspection | Statutory inspection certificate detail check | Third Party Inspector | Annually |
| 35 | Records, tagging system and equipment registers | Equipment inspection KPIs (percentage in-date, overdue items) reported to project management monthly | KPI dashboard/report | HSE Manager | Monthly |
| 36 | Records, tagging system and equipment registers | Barcode/QR-based equipment tracking system, where deployed, reconciled against physical asset count | Reconciliation report | HSE Officer | Monthly |
| 37 | Records, tagging system and equipment registers | Equipment demobilised from site has final inspection record closed out and archived | Demobilisation checklist and archive confirmation | Document Controller | Upon demobilisation |
| 38 | Records, tagging system and equipment registers | Insurance/third-party liability certificates for major plant items current and filed with equipment register | Insurance certificate copy on file | HSE Manager | Annually |
| 39 | Records, tagging system and equipment registers | Random equipment inspection audit conducted jointly with client/consultant representative | Joint audit report with findings | HSE Manager | Quarterly |
| 40 | Welding, cutting and hot work equipment | Welding machines inspected for earth cable continuity and cable insulation condition before use | Pre-use inspection checklist | Welder | Daily |
| 41 | Welding, cutting and hot work equipment | Hot work permit issued and equipment condition verified before commencing welding or grinding activity | Hot work permit with equipment checklist attached | HSE Officer | Before hot work |
| 42 | Welding, cutting and hot work equipment | Fire watch equipped with appropriate extinguisher positioned during and after hot work per permit duration | Fire watch log and extinguisher check | Fire Watcher | During/after hot work |
| 43 | Concrete and material handling equipment | Concrete pump boom and hopper inspected for structural cracks, hydraulic leaks and pipe clamp integrity before use | Pre-use inspection checklist | Pump Operator | Daily |
| 44 | Concrete and material handling equipment | Concrete mixer trucks inspected for drum condition, chute security and reversing alarm function | Pre-use inspection checklist | Driver/Operator | Daily |
| 45 | Concrete and material handling equipment | Tower crane and hoist material skips inspected for structural integrity, latch mechanism and load markings | Skip inspection checklist | Rigger | Weekly |
| 46 | Concrete and material handling equipment | Passenger/material hoists inspected and certified by competent person with interlocks tested functional | Hoist inspection certificate and interlock test record | Third Party Inspector | Monthly |
| 47 | Colour coding system administration | Site-wide colour coding scheme for equipment inspection established on a quarterly rotation basis | Colour coding procedure document with current quarter colour identified | HSE Manager | Quarterly |
| 48 | Colour coding system administration | Current inspection colour prominently displayed on notice boards and equipment yards | Photograph of posted colour code chart | HSE Officer | Quarterly |
| 49 | Colour coding system administration | Colour tags/tape applied to equipment matches the current valid quarter colour only | Spot check of tag colour vs published scheme | HSE Officer | Weekly |
| 50 | Colour coding system administration | Equipment bearing expired colour code removed from service until re-inspected and re-tagged | Removal from service log / tag replacement record | Site Supervisor | Weekly |
| 51 | Colour coding system administration | Colour code inspection register cross-referenced with third-party inspection certificates for lifting equipment | Register reconciled against LOLER-equivalent certification | HSE Officer | Monthly |
| 52 | Lifting equipment inspection (LOLER-style regime) | All lifting equipment and accessories (slings, shackles, chains) thoroughly examined by competent person at required intervals (6 months for lifting accessories, 12 months for lifting equipment not carrying persons) | Thorough examination certificate on file, in-date | Third Party Inspector | Per certificate interval |
| 53 | Lifting equipment inspection (LOLER-style regime) | Lifting equipment carrying persons (man-baskets, personnel platforms) examined at 6-monthly intervals minimum | Examination certificate specific to personnel-carrying equipment | Third Party Inspector | 6-Monthly |
| 54 | Lifting equipment inspection (LOLER-style regime) | Safe working load (SWL) or working load limit (WLL) clearly marked and legible on all lifting gear | Visual inspection of markings | HSE Officer | Weekly |
| 55 | Lifting equipment inspection (LOLER-style regime) | Lifting accessories with damage (cuts, corrosion, deformation) removed from service immediately and quarantined | Quarantine/scrap log with photographic evidence | Rigger/Banksman | Daily |
| 56 | Lifting equipment inspection (LOLER-style regime) | Pre-use visual inspection of slings and shackles conducted by rigger before each lift | Pre-use inspection checklist signed by rigger | Rigger | Daily / Before each lift |
| 57 | Lifting equipment inspection (LOLER-style regime) | Lifting plan prepared and approved for critical/tandem lifts, referencing examined equipment certificates | Approved lifting plan document | Lifting Supervisor | Before critical lift |
| 58 | Lifting equipment inspection (LOLER-style regime) | Crane and lifting appliance load charts available at the equipment and referenced during lift planning | Load chart present in cab / lift plan attachment | Crane Operator | Daily |
| 59 | Mobile and tower crane inspection | Tower cranes hold valid Dubai Municipality / Trakhees (as applicable) operating permit displayed on site | Permit certificate copy on file and displayed at crane base | HSE Manager | Annually / per permit validity |
| 60 | Mobile and tower crane inspection | Mobile and tower cranes undergo daily pre-operational checks by operator using OEM checklist | Daily pre-use inspection checklist signed by operator | Crane Operator | Daily |
| 61 | Mobile and tower crane inspection | Crane operators hold valid, applicable competency licence/certificate for equipment class operated | Licence copy verified against equipment type | HSE Officer | Before deployment |
| 62 | Mobile and tower crane inspection | Anemometer fitted and functional on tower cranes with wind speed cut-off limits enforced | Anemometer calibration/function check log | Crane Operator | Daily |
| 63 | Mobile and tower crane inspection | Crane erection, climbing and dismantling supervised by competent engineer with method statement in place | Method statement and supervision sign-off | Lifting Engineer | Per erection/climb |
| 64 | Mobile and tower crane inspection | Load moment indicator (LMI) and anti-two-block device tested functional before each shift | Functional test log | Crane Operator | Daily |
| 65 | Excavators, loaders and earthmoving equipment | Heavy equipment (excavators, loaders, dozers) undergo daily pre-start inspection using OEM checklist | Pre-start inspection checklist signed by operator | Plant Operator | Daily |
| 66 | Excavators, loaders and earthmoving equipment | Reverse alarms, horns and rotating beacons functional on all mobile plant | Functional check recorded on daily checklist | Plant Operator | Daily |
| 67 | Excavators, loaders and earthmoving equipment | Equipment operators hold valid competency card/licence appropriate to plant type | Operator competency card verification | HSE Officer | Before deployment |
| 68 | Excavators, loaders and earthmoving equipment | Equipment colour tag verified current before mobilisation to work front | Visual check by banksman/supervisor before use | Site Supervisor | Daily |
| 69 | Excavators, loaders and earthmoving equipment | Hydraulic hoses, buckets and attachments inspected for leaks, cracks and wear | Inspection checklist item recorded | Plant Operator | Daily |
| 70 | Excavators, loaders and earthmoving equipment | Seatbelt and ROPS/FOPS structure present and undamaged on all mobile plant | Visual inspection log | Plant Operator | Daily |
| 71 | Power tools and portable electrical equipment | Portable Appliance Testing (PAT) conducted on all portable electrical tools and equipment at scheduled intervals | PAT test label with pass date and next-due date visible | Electrical Supervisor | Quarterly |
| 72 | Power tools and portable electrical equipment | Damaged or untested electrical equipment removed from site immediately and tagged out of service | Tag-out record and equipment removal log | HSE Officer | As found |
| 73 | Power tools and portable electrical equipment | Power tool guards intact and functional, no bypassing of interlocks or guards observed | Visual inspection during site walk | HSE Officer | Weekly |
| 74 | Power tools and portable electrical equipment | Extension cables and reels inspected for insulation damage and correct earthing before use | Pre-use visual inspection | Worker | Daily |
| 75 | Power tools and portable electrical equipment | Residual current devices (RCDs) fitted to all temporary power supplies and tested functional | RCD test button check log | Electrical Supervisor | Weekly |
| 76 | Scaffolding and access equipment | Scaffold inspected and tagged by competent scaffold inspector before first use, weekly thereafter and after adverse weather | Scafftag inspection record with date and inspector signature | Scaffold Inspector | Weekly |
| 77 | Scaffolding and access equipment | Scaffold tag colour system matches current site colour code and indicates safe/incomplete/do-not-use status clearly | Scafftag colour and status verified against register | HSE Officer | Weekly |
| 78 | Scaffolding and access equipment | Mobile scaffold towers fitted with outriggers and locked castors before use, inspected before each shift | Pre-use checklist for mobile towers | User/Supervisor | Daily |
| 79 | Scaffolding and access equipment | Ladders inspected for damage, colour-coded/tagged and free from paint that could hide defects | Ladder inspection tag record | HSE Officer | Monthly |
| 80 | Pressure vessels, compressors and gas equipment | Air compressors and pressure vessels hold valid statutory inspection certificate per local authority requirement | Pressure vessel certificate on file, in-date | Third Party Inspector | Annually |
| 81 | Pressure vessels, compressors and gas equipment | Gas cylinders (oxygen/acetylene/LPG) stored upright, secured, segregated by type with colour-coded caps intact | Storage area inspection checklist | HSE Officer | Weekly |
| 82 | Pressure vessels, compressors and gas equipment | Pressure relief valves and gauges on compressed equipment tested functional per maintenance schedule | Maintenance test record | Plant Maintenance Team | Quarterly |
| 83 | Pressure vessels, compressors and gas equipment | Welding and cutting gas hoses inspected for leaks, cracks and correct flashback arrestors fitted | Pre-use hose inspection checklist | Welder | Daily |
| 84 | Records, tagging system and equipment registers | Master equipment register maintained listing all plant, inspection due dates and current colour code status | Equipment register reviewed and updated | HSE Manager | Monthly |
| 85 | Records, tagging system and equipment registers | Third-party inspection certificates for statutory equipment filed and accessible for audit within 24 hours | Document control retrieval test | Document Controller | Quarterly |
| 86 | Records, tagging system and equipment registers | Non-conformances from equipment inspections tracked in CAPA log with defined closure timeline | CAPA tracker with equipment ID cross-reference | HSE Manager | As occurs |
| 87 | Records, tagging system and equipment registers | Equipment found without valid colour tag or certificate immediately isolated with danger tag applied | Danger tag/lock-out record | HSE Officer | As found |
| 88 | Records, tagging system and equipment registers | Subcontractor-owned equipment mobilised to site subject to same colour coding and inspection verification before use | Mobilisation inspection checklist for subcontractor plant | HSE Officer | Before mobilisation |
Each checkpoint records Status (Yes / No / N/A), Comments, Corrective Action and Sign-off. Switch to Complete in-app to fill it here, or download the blank version to complete on site.
Next step
Turn this into evidence you can hand over
Replace scattered spreadsheets and WhatsApp threads with one HSE operations system built around UAE authority expectations.
- Built around UAE authoritiesADOSH-SF, Trakhees, DM, DCD, MOIAT and ISO 45001 structures.
- Usable the same dayTemplates and registers are pre-filled with your company details.
- Evidence, not just formsEvery record carries dates, signatures and an export you can hand over.