Part D — Risk & Change
MOC Closeout Checklist
Owner
HSE Manager / Document Controller
Review / trigger
Annual review; update on legal, authority, project or client change
Checkpoints
88
| # | Area | Checkpoint / Requirement | Evidence / Acceptance Criteria | Responsible | Frequency |
|---|---|---|---|---|---|
| 1 | MOC Initiation & Scope Verification | Original MOC request form retrieved and scope of change confirmed as fully implemented | Approved MOC form (MOC-01) cross-checked against as-built condition on site | MOC Coordinator | Per closeout |
| 2 | MOC Initiation & Scope Verification | Change category (temporary/permanent, like-for-like/non-like-for-like) reconfirmed at closeout | MOC register entry with category field validated | HSE Engineer | Per closeout |
| 3 | MOC Initiation & Scope Verification | Scope creep during implementation identified and documented as deviation | Deviation log attached to MOC file, signed by originator | Project Engineer | Per closeout |
| 4 | MOC Initiation & Scope Verification | Reason for change and hazard trigger re-verified against actual outcome | MOC justification section reviewed vs post-change condition | MOC Coordinator | Per closeout |
| 5 | MOC Initiation & Scope Verification | All interim/temporary MOCs linked to this change reviewed for closure or conversion to permanent | Temporary MOC tracker showing linked IDs closed | HSE Manager | Per closeout |
| 6 | MOC Initiation & Scope Verification | Affected disciplines (process, mechanical, electrical, civil, HSE) confirmed as consulted during review | Multidiscipline review sign-off sheet attached | MOC Coordinator | Per closeout |
| 7 | MOC Initiation & Scope Verification | MOC closeout initiated within company-defined timeframe of physical completion | Date-stamped closeout request vs completion certificate, per site OMS/PTW procedure | MOC Coordinator | Per closeout |
| 8 | MOC Initiation & Scope Verification | Change originator and area owner jointly confirm change matches original intent | Joint sign-off statement on MOC closeout form | Area Owner / Originator | Per closeout |
| 9 | Risk Assessment Review | Original MOC risk assessment (HAZID/HAZOP/What-if) revisited against final implemented condition | Risk assessment revision log with closeout annotation | HSE Engineer | Per closeout |
| 10 | Risk Assessment Review | New or residual hazards introduced during implementation identified and assessed | Updated risk register showing residual risk ranking | HSE Engineer | Per closeout |
| 11 | Risk Assessment Review | Risk mitigation measures listed in MOC verified as physically installed/functional | Field verification checklist with photos of installed controls | HSE Engineer / Discipline Engineer | Per closeout |
| 12 | Risk Assessment Review | ALARP demonstration reviewed and confirmed still valid post-implementation | ALARP justification note reviewed by HSE Manager | HSE Manager | Per closeout |
| 13 | Risk Assessment Review | Independent Protection Layers (IPLs) affected by change tested and confirmed operational | SIL/IPL verification test record | Instrumentation Engineer | Per closeout |
| 14 | Risk Assessment Review | Fire & gas detection coverage reassessed if layout/process change affects release scenarios | F&G mapping study update reference in MOC file | Process Safety Engineer | Per closeout |
| 15 | Risk Assessment Review | Risk assessment sign-off obtained from Process Safety / Technical Authority as applicable | Technical Authority endorsement recorded on MOC-02 form | Technical Authority | Per closeout |
| 16 | Risk Assessment Review | Bowtie or LOPA diagrams updated where change affects major accident hazard barriers | Revised bowtie diagram filed in document control, per SIA/OSHAD SF requirements | Process Safety Engineer | Per closeout |
| 17 | Engineering & Technical Documentation Update | P&IDs, PFDs and layout drawings updated to reflect final as-built change | Redlined drawings issued as 'As-Built' with revision number | Document Controller | Per closeout |
| 18 | Engineering & Technical Documentation Update | Equipment datasheets and specifications revised to match installed equipment | Updated datasheet matching nameplate data of installed item | Design Engineer | Per closeout |
| 19 | Engineering & Technical Documentation Update | Cause & effect matrices and control narratives updated for logic changes | Revised C&E matrix approved by Instrumentation Lead | Instrumentation Engineer | Per closeout |
| 20 | Engineering & Technical Documentation Update | Electrical single line diagrams updated for load or protection setting changes | Updated SLD with revision control stamp | Electrical Engineer | Per closeout |
| 21 | Engineering & Technical Documentation Update | Hazardous area classification drawings reviewed and revised if applicable | Updated Ex zoning drawing referencing IEC 60079-10 methodology | Electrical Engineer | Per closeout |
| 22 | Engineering & Technical Documentation Update | Piping class and material specification changes reflected in line list | Updated line list cross-referenced to isometrics | Piping Engineer | Per closeout |
| 23 | Engineering & Technical Documentation Update | Document register updated to supersede obsolete revisions and archive originals | Document control log showing supersession trail | Document Controller | Per closeout |
| 24 | Engineering & Technical Documentation Update | Digital twin / asset information model (if used) synchronised with as-built change | IT/Engineering confirmation of model update | Engineering Systems Custodian | Per closeout |
| 25 | Operating Procedures & SOP Update | Standard Operating Procedures affected by the change identified via impact assessment | SOP impact assessment checklist completed | Operations Engineer | Per closeout |
| 26 | Operating Procedures & SOP Update | Start-up, normal operating and shutdown procedures revised to reflect new configuration | Revised SOP issued with new revision date and approval | Operations Supervisor | Per closeout |
| 27 | Operating Procedures & SOP Update | Emergency response and shutdown (ESD) procedures updated where change affects safety systems | Updated ERP/ESD procedure filed with document control | HSE Manager | Per closeout |
| 28 | Operating Procedures & SOP Update | Permit to work procedure annotations updated if change affects isolation points | Updated isolation schedule/LOTO point list | PTW Coordinator | Per closeout |
| 29 | Operating Procedures & SOP Update | Simultaneous Operations (SIMOPS) matrix reviewed for continued validity | Revised SIMOPS matrix signed by Operations Manager | Operations Manager | Per closeout |
| 30 | Operating Procedures & SOP Update | Operator round sheets and checklists updated to include new equipment/parameters | Updated round sheet template distributed to control room | Shift Supervisor | Per closeout |
| 31 | Operating Procedures & SOP Update | Draft/interim procedures used during transition formally withdrawn and archived | Interim procedure withdrawal notice issued | Document Controller | Per closeout |
| 32 | Operating Procedures & SOP Update | Maintenance procedures and preventive maintenance plans updated for new/modified equipment | Updated CMMS maintenance plan reference number | Maintenance Engineer | Per closeout |
| 33 | Training & Competency Verification | Training needs analysis completed for personnel affected by the change | TNA record signed by department head | Training Coordinator | Per closeout |
| 34 | Training & Competency Verification | Toolbox talk / awareness briefing delivered to all affected operating and maintenance staff | Signed attendance sheet with briefing content reference | Area Supervisor | Per closeout |
| 35 | Training & Competency Verification | Formal training sessions on new equipment/process conducted where required | Training attendance record and competency test result | Training Coordinator | Per closeout |
| 36 | Training & Competency Verification | Competency of operators verified before change handed to routine operation | Competency assessment/sign-off form | Operations Manager | Per closeout |
| 37 | Training & Competency Verification | Contractor/third-party personnel briefed on change if it affects their work area | Contractor briefing acknowledgment log | HSE Officer | Per closeout |
| 38 | Training & Competency Verification | Emergency responders briefed on new hazards or altered emergency response arrangements | Fire team/ERT briefing record | HSE Manager | Per closeout |
| 39 | Training & Competency Verification | Training records filed and linked to individual employee competency files | HR/competency management system entry reference | Training Coordinator | Per closeout |
| 40 | Training & Competency Verification | Refresher training schedule established for periodic reinforcement if change is complex | Training calendar entry approved by department head | Training Coordinator | Per closeout |
| 41 | Physical Verification & Pre-Startup Safety Review | Pre-Startup Safety Review (PSSR) conducted prior to introducing change into service | Completed PSSR checklist signed by multidisciplinary team | PSSR Team Lead | Per closeout |
| 42 | Physical Verification & Pre-Startup Safety Review | Field walkdown performed to confirm installation matches approved design and drawings | Walkdown checklist with photographic evidence | Site Engineer | Per closeout |
| 43 | Physical Verification & Pre-Startup Safety Review | Punch list items from construction/installation closed out or formally deferred with approval | Punch list tracker showing zero open critical items | Construction Manager | Per closeout |
| 44 | Physical Verification & Pre-Startup Safety Review | Equipment tagging, labelling and signage updated to reflect new configuration | Site photos confirming updated labels/tags | Site Supervisor | Per closeout |
| 45 | Physical Verification & Pre-Startup Safety Review | Pressure testing, calibration and functional testing certificates verified as complete | Test certificates filed in MOC closeout package | QA/QC Engineer | Per closeout |
| 46 | Physical Verification & Pre-Startup Safety Review | Isolation certificates and de-isolation confirmed complete with no residual boundary in place | De-isolation certificate signed by Responsible Person | Isolation Authority | Per closeout |
| 47 | Physical Verification & Pre-Startup Safety Review | Housekeeping and site clearance of the change area confirmed prior to closeout | Site inspection sign-off | HSE Officer | Per closeout |
| 48 | Physical Verification & Pre-Startup Safety Review | Interim risk controls (temporary barriers, watchman, etc.) removed only after permanent measures verified | Removal record cross-referenced to permanent control verification | HSE Officer | Per closeout |
| 49 | Regulatory, Insurance & Third-Party Compliance | Change assessed against applicable Civil Defence requirements where fire/life safety systems affected | Civil Defence NOC/approval letter referenced in MOC file, per UAE Civil Defence Authority requirements | HSE Manager | Per closeout |
| 50 | Regulatory, Insurance & Third-Party Compliance | Municipality or relevant Emirate authority approvals obtained/updated for structural or layout changes | Municipality approval/permit copy attached | Project Manager | Per closeout |
| 51 | Regulatory, Insurance & Third-Party Compliance | Third-party inspection body (TPI) certification updated for pressure equipment/lifting equipment changes | TPI certificate with updated equipment details | QA/QC Engineer | Per closeout |
| 52 | Regulatory, Insurance & Third-Party Compliance | Insurance provider notified of material changes affecting insured risk profile where required | Notification correspondence and insurer acknowledgment | Risk Manager | Per closeout |
| 53 | Regulatory, Insurance & Third-Party Compliance | Environmental permit conditions reviewed for continued compliance following the change | Environmental permit compliance checklist referencing EAD/local EHS Centre requirements | Environmental Officer | Per closeout |
| 54 | Regulatory, Insurance & Third-Party Compliance | ADNOC/client-specific MOC governance requirements (if applicable) satisfied and evidenced | Client MOC approval record attached | MOC Coordinator | Per closeout |
| 55 | Regulatory, Insurance & Third-Party Compliance | Statutory equipment registration updated with Ministry of Human Resources & Emiratisation (MOHRE) records where applicable | Updated equipment registration certificate | HSE Manager | Per closeout |
| 56 | Regulatory, Insurance & Third-Party Compliance | Legal register updated to reflect any new applicable legislation or standard triggered by the change | Legal register revision entry | Compliance Officer | Per closeout |
| 57 | MOC Package Documentation & Sign-off | Complete MOC closeout package compiled including all supporting evidence and certificates | MOC closeout package index with all attachments verified present | MOC Coordinator | Per closeout |
| 58 | MOC Package Documentation & Sign-off | All required approver signatures obtained per MOC authorisation matrix | Signed MOC-03 closeout form matching authorisation matrix levels | MOC Coordinator | Per closeout |
| 59 | MOC Package Documentation & Sign-off | Cost and schedule variance from original MOC recorded for lessons learned | Variance summary section completed in closeout form | Project Controls Engineer | Per closeout |
| 60 | MOC Package Documentation & Sign-off | Lessons learned captured and shared with relevant stakeholders/HSE committee | Lessons learned register entry and distribution record | HSE Manager | Per closeout |
| 61 | MOC Package Documentation & Sign-off | MOC register status updated from 'open/in-progress' to 'closed' | MOC tracking register showing closed status and closure date | MOC Coordinator | Per closeout |
| 62 | MOC Package Documentation & Sign-off | Audit trail of all revisions to MOC documentation retained and version controlled | Document control version history report | Document Controller | Per closeout |
| 63 | MOC Package Documentation & Sign-off | Closeout package archived per company document retention policy | Archival confirmation with retention period noted | Document Controller | Per closeout |
| 64 | MOC Package Documentation & Sign-off | Post-closeout review scheduled (30/60/90-day) to confirm sustained effectiveness of change | Post-closeout review schedule entry in HSE calendar | HSE Manager | Per closeout |
| 65 | Post-Implementation Performance Monitoring | Key performance indicators defined in MOC monitored for expected outcome achievement | KPI tracking sheet with baseline vs actual comparison | Process Engineer | Monthly for 3 months post-closeout |
| 66 | Post-Implementation Performance Monitoring | Incident/near-miss data for the changed area monitored for any correlation to the change | Incident trend report filtered by area/equipment tag | HSE Manager | Monthly for 3 months post-closeout |
| 67 | Post-Implementation Performance Monitoring | Equipment performance/reliability data reviewed against design intent of the change | Reliability report from CMMS/maintenance data | Reliability Engineer | Quarterly post-closeout |
| 68 | Post-Implementation Performance Monitoring | Feedback from operators and maintenance crews collected on practical workability of the change | Feedback log/survey results summarised | Operations Supervisor | Per closeout + 30 days |
| 69 | Post-Implementation Performance Monitoring | Any unresolved action items from PSSR tracked to closure with target dates | Action tracking log with overdue items highlighted | MOC Coordinator | Monthly until closed |
| 70 | Post-Implementation Performance Monitoring | Emergency drill or scenario testing conducted if change materially affects emergency response | Drill report referencing changed scenario | HSE Manager | Within 90 days of closeout |
| 71 | Post-Implementation Performance Monitoring | Change communicated to sister sites/similar facilities where hazard learning is transferable | Cross-site alert/bulletin issuance record | HSE Manager | Per closeout |
| 72 | Post-Implementation Performance Monitoring | Final MOC effectiveness review signed off confirming no re-opening required | Effectiveness review sign-off form | MOC Owner | At 90-day review |
| 73 | Contractor & Stakeholder Coordination | Contractor scope of work updated to reflect final change and formally re-issued | Revised contractor SOW/work order with acknowledgment | Contracts Engineer | Per closeout |
| 74 | Contractor & Stakeholder Coordination | Subcontractors working in the changed area briefed and their method statements revised | Updated method statement approval record | Site Supervisor | Per closeout |
| 75 | Contractor & Stakeholder Coordination | Interface points with adjacent contractors/departments re-confirmed post-change | Interface management log updated | Interface Coordinator | Per closeout |
| 76 | Contractor & Stakeholder Coordination | Vendor/OEM confirmation obtained that installed modification does not void warranty | OEM confirmation letter or email on file | Procurement Engineer | Per closeout |
| 77 | Contractor & Stakeholder Coordination | Spare parts and inventory records updated to reflect new/modified equipment | Updated spares list in inventory management system | Warehouse/Maintenance Planner | Per closeout |
| 78 | Contractor & Stakeholder Coordination | Emergency contact and stakeholder distribution list updated if change affects responsible personnel | Updated contact list circulated to control room | Administration Officer | Per closeout |
| 79 | Contractor & Stakeholder Coordination | Client/owner representative formal acceptance obtained for handover of the changed asset | Handover certificate signed by client representative | Project Manager | Per closeout |
| 80 | Contractor & Stakeholder Coordination | Any outstanding commercial/contractual claims arising from change implementation logged and tracked | Claims register entry with status | Commercial Manager | Per closeout |
| 81 | Verification of Original MOC Approval Conditions | All pre-conditions stipulated at MOC approval stage verified as satisfied before closure | Pre-condition checklist with evidence cross-references | MOC Coordinator | Per closeout |
| 82 | Verification of Original MOC Approval Conditions | Time-bound temporary approvals checked against expiry date and either closed or formally extended | Approval validity tracker with extension approvals if any | MOC Coordinator | Per closeout |
| 83 | Verification of Original MOC Approval Conditions | Budget approval limits compared to actual expenditure and variance justified | Cost reconciliation sheet approved by finance/project control | Project Controls Engineer | Per closeout |
| 84 | Verification of Original MOC Approval Conditions | Any conditions requiring Technical Authority re-endorsement at closeout formally obtained | Technical Authority closeout endorsement | Technical Authority | Per closeout |
| 85 | Verification of Original MOC Approval Conditions | Change classification (minor/major) reconfirmed did not escalate during implementation requiring re-approval | Classification review note in closeout file | HSE Manager | Per closeout |
| 86 | Verification of Original MOC Approval Conditions | Linked permits to work referencing the MOC formally closed and cross-referenced | PTW closure record cross-referenced to MOC number | PTW Coordinator | Per closeout |
| 87 | Verification of Original MOC Approval Conditions | Non-conformances raised during implementation tracked to resolution with root cause noted | NCR register entry closed with root cause and corrective action | QA/QC Engineer | Per closeout |
| 88 | Verification of Original MOC Approval Conditions | Final management review and formal sign-off declaring MOC fully closed | Management sign-off on MOC closure certificate | Site/Plant Manager | Per closeout |
Each checkpoint records Status (Yes / No / N/A), Comments, Corrective Action and Sign-off. Switch to Complete in-app to fill it here, or download the blank version to complete on site.
Next step
Turn this into evidence you can hand over
Replace scattered spreadsheets and WhatsApp threads with one HSE operations system built around UAE authority expectations.
- Built around UAE authoritiesADOSH-SF, Trakhees, DM, DCD, MOIAT and ISO 45001 structures.
- Usable the same dayTemplates and registers are pre-filled with your company details.
- Evidence, not just formsEvery record carries dates, signatures and an export you can hand over.