Site Safety UAE
Heat Stress Daily Check — Supervisor Software Form
UAE Midday Break Law · MOHRE Decree 401 · ADOSH-SF · Dubai Municipality
Form: SSU-HS-DC-01
Rev: 1.0
Retain: Daily site record
1. Midday Break Compliance (15 Jun – 15 Sep · 12:30 – 15:00)
2. WBGT Readings & Work / Rest Cycle
Acclimatised: ≤ 28 continuous · 28–30 45/15 · 30–32 30/30 · > 32 stop
| Time | Location / area | WBGT (°C) | Work load (L/M/H) | Work / rest cycle applied | Action taken |
|---|---|---|---|---|---|
| 07:00 | |||||
| 09:00 | |||||
| 11:00 | |||||
| 13:00 | |||||
| 15:00 | |||||
| 17:00 |
3. Water, Shade & Cooling Provision
4. Pre-Shift Worker Checks (record any concerns)
5. Heat-Related Incidents & Stop-Work
Site Supervisor
Name & signatureDate / time
HSE Officer
Name & signatureDate / time
Project Manager
Name & signatureDate / time
Tip: choose A4 paper and portrait orientation in the print dialog.